Jump to content

MRT Line 3 (Metro Manila)

From Wikipedia, the free encyclopedia
(Redirected from Metrostar Express)

MRT Line 3
An MRTC 3000 class train passing the Ortigas Interchange in October 2023
Overview
Native nameFilipino: Ikatlong Linya ng Sistema ng Kalakhang Riles Panlulan ng Maynila
StatusOperational
OwnerMetro Rail Transit Corporation
Line number3
LocaleMetro Manila, Philippines
Termini
Stations13[1]
Websitewww.dotrmrt3.gov.ph
Service
TypeLight rapid transit
SystemManila Metro Rail Transit System
Services1[1]
Operator(s)Department of Transportation
Depot(s)North Avenue
Rolling stockMRTC 3000 class[1]
MRTC 3100 class[1]
Daily ridership357,198 (2023)[2]
Ridership129,030,158 (2023)[2]
History
CommencedOctober 15, 1996; 28 years ago (1996-10-15)
OpenedDecember 15, 1999; 25 years ago (1999-12-15)
CompletedJuly 20, 2000; 24 years ago (2000-07-20)
Technical
Line length16.9 km (10.5 mi)
Number of tracksDouble
CharacterGrade separated
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Loading gauge3,730 mm × 2,600 mm (12 ft 3 in × 8 ft 6 in)[3]
Minimum radius370 m (1,210 ft) (mainline)
25 m (82 ft) (depot)
Electrification750 V DC overhead catenary
Operating speed60 km/h (37 mph)
SignallingAlstom CITYFLO 250 fixed block with subsystems of EBICAB 900 ATP, EBI Screen 900 CTC, and EBI Lock 950 CBI
Maximum incline4% (mainline)
5% (depot spur line)[4]
Average inter-station distance1.28 km (0.80 mi)
Route map

Up arrow Quirino Highway
 MMS 
Left arrow Dr. Santos
North Avenue
San Jose Del Monte Right arrow
North Avenue Depot
Quezon Avenue
Left arrow Lerma - University Avenue Right arrow
  FTI Right arrow
  NAIA Terminal 3 Right arrow
 MMS 
GMA–Kamuning
Left arrow Recto - Antipolo Right arrow
Araneta Center–Cubao
Santolan–Annapolis
Ortigas
Shaw Boulevard
Boni
Guadalupe
Left arrow Ayala - Guadelupe Right arrow
5
Buendia
Ayala
5 Bus interchange
Magallanes
Bus interchange
Left arrow Valenzuela-Gov. Pascual / Tutuban
  FTI / Alabang / Calamba Right arrow
Taft Avenue
Left arrow Fernando Poe Jr. - Dr. Santos - Niog Right arrow

The Metro Rail Transit Line 3, also known as the MRT Line 3, MRT-3, or Metrostar Express, is a rapid transit line in Metro Manila in the Philippines. The line runs in an orbital north to south route following the alignment of Epifanio de los Santos Avenue (EDSA). Despite its name, the line is more akin to a light rapid transit system owing to its tram-like rolling stock while having total grade separation and high passenger throughput.[5] The line is officially known as the Yellow Line. Its current General Manager is Oscar Bongon.[6]

Envisioned in the 1970s and 1980s as part of various feasibility studies, the 13-station, 16.9-kilometer (10.5 mi) line was the second rapid transit line to be built in Metro Manila when it started full operations in 2000. The line is owned by the Metro Rail Transit Corporation (MRTC) under a 25-year build–lease–transfer agreement with the Philippine government's Department of Transportation (DOTr), who operates the line.[7]

The line is integrated with the public transit system in Metro Manila, where passengers also take various forms of road-based public transport, such as buses, to and from a station to reach their intended destination. Serving close to 360,000 passengers on a daily basis, the line is the busiest among Metro Manila's three rapid transit lines.[8] Total ridership significantly exceeds its built maximum capacity of 350,000 passengers a day, with various solutions being proposed or implemented to alleviate chronic congestion. Expanding the network's capacity to accommodate the rising number of passengers is currently set on tackling this problem.

History

[edit]

Early planning

[edit]
A northbound train leaving Shaw Boulevard station
Taft Avenue station platform area

In 1973, the Overseas Technical Cooperation Agency (OTCA; predecessor of the Japan International Cooperation Agency) presented a plan to construct five subway lines in Metro Manila. The study was known as the Urban Transport Study in the Manila Metropolitan Area. One of the five lines, Line 3, was planned as a 24.3-kilometer (15.1 mi) line along Epifanio de los Santos Avenue (EDSA), the region's busiest road corridor. The plan would have resolved the traffic problems of Metro Manila and would have taken 15 years to complete.[9]

Another study by JICA was presented in 1976 which included the five lines proposed in 1973. The study recommended heavy rail due to the rising population.[9]

During the construction of the first line of the Manila Light Rail Transit System in the early 1980s, Electrowatt Engineering Services of Zürich designed a comprehensive plan for metro service in Metro Manila. The plan—still used as the basis for planning new metro lines—consisted of a 150-kilometer (93 mi) network of rapid transit lines spanning all major corridors within 20 years.[10] The study integrated the previous 1973 OTCA study, the 1976 JICA study, and the 1977 Freeman Fox and Associates study, which was used as the basis for the LRT Line 1.[9]

Development and early delays

[edit]

The project was restarted as a light rail project in 1989. DOTC planned to construct a light railway transit line along EDSA, a major thoroughfare in Metropolitan Manila, which would traverse the cities of Quezon, Mandaluyong, Makati, and Pasay. The plan, referred to as EDSA Light Rail Transit III (EDSA LRT III), was intended to provide a mass transit system along EDSA and alleviate the congestion and growing transportation problems in the metropolis. On March 3, 1990, a letter of intent was sent by Eli Levin Enterprises, Inc., represented by Elijahu Levin, to the Department of Transportation and Communications (DOTC), now Department of Transportation (DOTr), secretary Oscar Orbos, proposing to construct the EDSA LRT III on a build-operate-transfer (BOT) basis.[11]

On July 9, 1990, President Corazon Aquino signed Republic Act No. 6957, simply known as the Build-Operate-Transfer (BOT) Law; it took exactly three months later. The government then published an invitation to pre-qualify and bid for the project on February 21, 1991.[11] Five groups responded to the invitation: ABB Trazione of Italy, Hopewell Holdings Ltd. of Hong Kong, Mansteel International of Mandaue, Cebu, Mitsui & Co., Ltd. of Japan, and EDSA LRT Consortium, composed of ten foreign and domestic corporations: namely, Kaiser Engineers International, Inc., ACER Consultants (Far East) Ltd. and Freeman Fox (both later merged with Hyder Consulting), Tradeinvest/ČKD Tatra of the Czech and Slovak Federal Republics, TCGI Engineering All Asia Capital and Leasing Corporation, The Salim Group of Jakarta, E. L. Enterprises, Inc., and A.M. Oreta & Co. Capitol Industrial Construction Group, Inc., and F. F. Cruz & Co., Inc. EDSA LRT Consortium was the sole firm that passed the pre-qualification process, and submitted its proposal to the DOTC on July 16.[11][12] The Build-lease-Transfer (BLT) agreement was signed on November 7.[12]

On September 22, 1992, DOTC and EDSA LRT Corporation signed a revised and restated BLT Agreement. The new BLT Agreement defined the project coverage in two phases: Phase 1, which spanned 16 kilometers (9.9 mi) between North Avenue, Quezon City and Taft Avenue, Pasay, and Phase II, which spanned 5.5 kilometers (3.4 mi) from North Avenue to Monumento, Caloocan.[12] The project was approved by the Cabinet on January 19, 1993.[12] On May 6 of that same year, the project was launched by President Fidel V. Ramos.[13]

According to the agreements, the EDSA LRT III will use light rail vehicles from the Czech and Slovak Federal Republics and will have a maximum carrying capacity of 450,000 passengers a day, or 150 million a year to be achieved, through 54 such vehicles operating simultaneously. The EDSA LRT III will run at grade, or street level, on the mid-section of EDSA for a distance of 17.8 kilometers (11.1 mi) from F.B. Harrison, Pasay, to North Avenue, Quezon City. The system will have its own power facility. It will also have thirteen (13) passenger stations and one depot on 16-hectare (40-acre) government property at North Avenue.[11]

However, construction could not commence, with the project stalled as the Philippine government conducted several investigations into alleged irregularities with the project's contract.[14][15] The Supreme Court had a case barring Eli Levin from implementing the project in March 1994, and the bids were ABB and Mitsubishi Corporation, which also wanted to supply contracts.[14]

A year later, the Supreme Court upheld the regularity of the project which paved the way for construction to finally begin during the term of President Ramos.[11] A consortium of local companies, led by Fil-Estate Management was later joined by Ayala Land, and 5 others, later formed the Metro Rail Transit Corporation (MRTC) in June 1995 and took over the EDSA LRT Corporation.[16]

Construction and opening

[edit]
A train at Magallanes station in 2001.

On March 27, 1996, the unveiling marker was attended by President Ramos and others.[15] The MRTC was subsequently awarded a Build-Lease-Transfer contract by the DOTC, which meant that the latter would possess ownership of the system after the 25-year concession period. Meanwhile, the DOTC would assume all administrative functions, such as the regulation of fares and operations, leaving the MRTC responsibility over construction and maintenance of the system as well as the procurement of spare parts for trains. MRTC would later transfer the responsibility of maintaining the system to the DOTC in November 2010. In exchange, the DOTC would pay the MRTC monthly fees for a certain number of years to reimburse any incurred costs.[1]

Construction began on October 15 of the same year, with a BLT agreement signed between the Philippine government and the MRTC.[16] An amended turnkey agreement was later signed on September 16, 1997, with Sumitomo Corporation and Mitsubishi Heavy Industries. Sumitomo and Mitsubishi subcontracted EEI Corporation and AsiaKonstrukt for the civil works.[17] A separate agreement was signed with ČKD Dopravní Systémy (ČKD Tatra, now part of Siemens AG), the leading builder of trams and light rail vehicles for the Eastern Bloc, on rolling stock. MRTC also retained the services of ICF Kaiser Engineers and Constructors to provide program management and technical oversight of the services for the design, construction management, and commissioning.[1] MRTC would later sign a maintenance agreement with Sumitomo and Mitsubishi for the maintenance of the line on December 10 of the same year.[18]

During construction, the MRTC oversaw the design, construction, equipping, testing, and commissioning, while the DOTC oversaw technical supervision of the project activities covered by the BLT contract between the DOTC and MRTC. The DOTC also sought the services of SYSTRA, a French consultant firm, with regards to the technical competence, experience and track record in the construction and operations.[1]

On December 15, 1999, the initial section from North Avenue to Buendia was inaugurated by President Joseph Estrada,[19] with all remaining stations opening on July 20, 2000, a little over a month past the original deadline, due to DOTC's inclusion of additional work orders such as the Tramo flover in Pasay leading to Ninoy Aquino International Airport.[20] However, ridership was initially far below expectations when the line was still partially open, with passengers complaining of the tickets' steep price and the general lack of connectivity of the stations with other modes of public transportation.[21] Passengers' complaints of high ticket prices pointed to the maximum fare of 34 (equivalent to ₱79.21 in 2021), which at the time was significantly higher than a comparable journey on those lines operated by the LRTA and the PNR or a similar bus ride along EDSA. Although the MRTC projected 300,000–400,000 passengers riding the system daily, in the first month of operation the system saw a ridership of only 40,000 passengers daily (the ridership improved quickly, however, when passengers experienced significantly faster and convenient travel along EDSA, which experience soon spread by word of mouth).[22] The system was also initially criticized as a white elephant, comparing it to the Manila Light Rail Transit System and the Metro Manila Skyway.[23] To alleviate passenger complaints, the MRTC later reduced passenger fares to ₱15 (equivalent to ₱34.95 in 2021), as per the request of then-President Joseph Estrada and a subsequent government subsidy.

During the line's construction in 2000, Pasay residents raised concerns about the line being constructed at ground level, resulting in the closure of several intersections along EDSA, forcing people to take long detours just to cross EDSA. Residents also complained that they were not properly consulted about the line's construction in their area. The MRTC stated that the segment could not be made as an elevated railway due to the air rights above the LRT-1 already being awarded to the Department of Public Works and Highways for a flyover in 1996.[24]

Overcrowding and later decline

[edit]

MRTC projected a capacity breach in the system by 2002. By 2004, the line had the highest ridership of the three lines, with 400,000 passengers daily.[26] By early 2012, the system was carrying around 550,000 to 600,000 commuters during weekdays and was often badly overcrowded during peak times of access during the day and night. The line operated beyond its original designed capacity from 2004 to 2019.[27] In 2011, Sumitomo, through TES Philippines, issued a warning about the overcrowding situation of the line, in which a failure to immediately upgrade the line's trains and systems would result in damage to the trains and systems.[28]

By October 2012, DOTC removed Sumitomo as the maintenance provider of the line due to the high costs of the contract. With the entry of the joint venture of Philippine Trans Rail Management and Services Corporation (PH Trams) and Comm Builders & Technology Philippines Corporation (CB&T) as the maintenance provider in 2012,[29] and APT Global in 2013,[30] it marked the start of the deterioration of the line due to poor maintenance by the aforementioned maintenance providers that DOTC appointed. In 2014, there were reported daily incidents and disruptions, and a derailment of one train coach on August 13 of that year.[31] The government of Benigno Aquino III had been planning to buy the line from the MRT Corporation (MRTC), the private concessionaire that built the line, and then bid it out to private bidders. The Aquino government accused the MRTC of neglecting and not improving the services of the line under its watch.[32]

In February 2016, the Philippine Senate released a report stating that DOTC Secretary Jun Abaya and other DOTC officials "may have violated" the Anti-Graft and Corrupt Practices Act in relation to questionable contracts with the subsequent maintenance providers.[33] In a Senate report where the line's condition was found to be in "poor maintenance" as per studies made by MTR HK, DOTC officials were reported to be involved in graft in relation to questionable contracts, especially those for the maintenance of the line.[34]

The DOTC tried to bid out a three-year maintenance contract in 2014 and 2015, but both biddings failed because no bidders submitted a bid.[35][36] Through a negotiated procurement,[37] the Busan joint venture, a joint venture of Busan Transportation Corporation, Edison Development & Construction, Tramat Mercantile Inc., TMICorp Inc., and Castan Corporation, was awarded a three-year maintenance contract by the DOTC. The contract started in January 2016 and was slated to end by January 2019.[38] In 2017, DOTC's succeeding agency, the Department of Transportation (DOTr) attributed the operation's disruptions of the rail system to the Busan joint venture, later known as Busan Universal Rail, Inc. (BURI), with DOTr Transport Undersecretary for Rails Cesar Chavez noting 98 service interruptions and 833 passenger unloadings (or average of twice daily) as well as train derailments in April–June 2017.[25] BURI insisted that the disruptions the railway line was experiencing is due to "inherent design and quality concerns" and not to poor maintenance or normal tear or wear. It said that glitches started occurring since 2000, a claim that MRTC dismissed when Sumitomo was maintaining the system.[39] The maintenance contract was terminated on November 6, 2017.[40]

Capacity expansion

[edit]
The trains procured under the capacity expansion project in November 2016.
Part of the capacity expansion is the conversion of three-car trains to four-car trains with increased capacity.[41]

Due to the high ridership of the line, a proposal under study by the DOTC and NEDA proposed to double the current capacity by acquiring additional light rail vehicles to accommodate over 520,000 passengers a day.[42]

In January 2014, the DOTC entered into a contract with CNR Dalian for the procurement of 48 light rail vehicles. The trains, commonly referred to as the Dalian trains, were delivered in batches from 2015 to 2017. The introduction of the new trains would have allowed the line to handle over 800,000 passengers.[43] The Dalian trains entered revenue service in May 2016.[44] However, these became a subject of controversy among government officials, citing its incompatibility with the signaling system and weight limits on tracks. Later, it was revealed that several adjustments to the Dalian trains were required prior to revenue run deployment.[45] The train manufacturer CRRC Dalian has agreed to amend the train specifications to match the contract terms at no cost, and will do so in the soonest possible time.[46] Due to the trains undergoing the said adjustments, they were slowly introduced into regular operations, which led to the start of the gradual deployment on October 27, 2018.[47]

Aside from the procurement of the new trains, the capacity expansion project included the upgrading of the ancillary systems such as the power supply, overhead lines, the extension of the pocket track near Taft Avenue station and the modification of the turn back siding north of the North Avenue station.[48][49] The original plan also included the upgrading of the signaling system.[48] These upgrades, except for the upgrades to the Taft Avenue pocket track and the North Avenue turn back siding, would only be realized as part of the line's rehabilitation.

Plans were also laid to increase the number of cars in each train set, from the current three cars to four cars, which also increases the number of passengers being accommodated for each trip, from 1,182 passengers to 1,576.[50] The first mention of this plan was in 2013, during the procurement of the new trains.[4] However, in January 2016, an anonymous railway expert warned that the power supply at that time was not capable of handling four-car operations.[51] Despite this, four-car operations were first tested in a Dalian train in May 2016.[52] After the rehabilitation of the line which included the upgrading of the power supply, a dynamic test run for the use of four-car trains for regular operations was conducted on March 9, 2022.[53] Regular four-car operations began in the same month, initially deploying two trains for daily operations, subsequently increased to four.[54][55] Although full conversion was initially planned to be achieved by 2023,[56] all trains reverted to the existing 3-car configuration a few months after the months-long free rides ended.

Rehabilitation

[edit]
A vital aspect of the rehabilitation of the line was the replacement of worn-out rails.[57]

As early as 2011, there were proposals to rehabilitate the line. An unsolicited proposal were made by Metro Pacific Investments in 2011 at a cost of ₱25.1 billion. Another proposal was presented in 2014 at a cost of ₱23.3 billion.[58] In 2017, in the wake of various daily service interruptions in the line, San Miguel Corporation expressed its interest to rehabilitate the line.[59] That same year, Metro Pacific submitted another ₱20 billion proposal to rehabilitate, operate and maintain the line.[60] These proposals however would be rejected by the government.

Following the termination of the maintenance contract with Busan Universal Rail, Inc., the DOTr announced on November 29, 2017, that a government-to-government agreement between the Philippines and Japan would be signed by the end of that year, paving the way for Sumitomo Corporation to return as the maintenance provider of the line. The three-year contract would cover the rehabilitation and maintenance of the line.[61] The ₱22 billion project, partly funded by a ₱18 billion loan from the Japan International Cooperation Agency,[62] was approved by the Investment Coordination Committee (ICC) board of the National Economic and Development Authority (NEDA) on August 17, 2018.[63] It intended to rehabilitate and upgrade the existing systems and trains, for the line to return to its original high-grade design. The project was part of the Build! Build! Build! infrastructure program.

On November 8, 2018, the loan agreement for the project was signed,[62] while the rehabilitation and maintenance contract was signed on December 28.[64] The project was initially slated to start by January 2019,[65] but the implementation of a re-enacted government budget for 2019 and finalization of documents caused repeated delays on when the project could start,[66][67] which only started on May 1, 2019.[68]

Commemorative plaque to mark the completion of the rehabilitation project at Quezon Avenue station.

Under the 43-month contract, which was undertaken by Sumitomo, Mitsubishi Heavy Industries Engineering (MHIENG; part of the Mitsubishi Heavy Industries [MHI] group),[69] and TES Philippines, rehabilitation works were to be done within 26 months.[70] It covers the overhaul of all MRTC Class 3000 vehicles[e], repairs on the escalators and elevators, rail replacement, upgrades on the signaling and communication systems, power supply, overhead systems, maintenance and station equipment.[71] After the rehabilitation, a 17-month maintenance contract will be undertaken by the Japanese firms.[69] The contract was originally slated to end by December 31, 2022, or 43 months after the start of rehabilitation,[64] but was moved to May 31, 2023.[41][69]

The rehabilitation was originally scheduled to be completed by July 2021. However, delays brought by the COVID-19 pandemic[72] delayed its completion to the following December.[73] The project was completed on the aforementioned date, as announced by Transportation Secretary Arthur Tugade on February 28, 2022.[74] On March 22, President Rodrigo Duterte and Secretary Tugade inaugurated the newly rehabilitated line at a completion ceremony held at Shaw Boulevard station.[75][69] As part of its completion, free rides were offered initially for a month to combat inflation,[76] but was extended twice until June 30.[77]

On May 26, 2023, a ₱6.9 billion loan was signed by the governments of Japan and the Philippines for the second phase of the project, covering the line's continued maintenance and its connection to the North Triangle Common Station with the lines that would interchange at that station.[78] Four days later, DOTr and Sumitomo signed a contract to extend the latter's maintenance in the railway line until July 31, 2025.[79] Among the projects included under the new contract is the conversion of the trains used on the line from the present three railcars to four, following the previous test runs for the four-car trains in 2022,[41] and the expansion of the Taft Avenue pocket track to cater longer trains, allowing the pocket track to cater 4-car trains. Construction works for the pocket track extension began in November 2024. The program aims to increase the line's ridership capacity to 500,000 passengers a day.[80]

Route

[edit]
A Class 3000 train approaching Ayala station

The lines run along the alignment of Epifanio de los Santos Avenue from North Avenue in Quezon City to the intersection of EDSA and Taft Avenue in Pasay. The rails are mostly elevated and erected either over or along the roads covered, with cut and underground sections between Buendia and Ayala stations, the only underground stations on the line. The rail line serves the cities of Pasay, Makati, Mandaluyong, San Juan and Quezon City. The line crosses Osmeña Highway and South Luzon Expressway (SLEX) at Magallanes Interchange in Makati.

Stations

[edit]

The line has 13 stations along its 16.9-kilometer (10.5 mi) route,[1] spaced on average around 1.3 kilometers (0.81 mi) apart.[1] The southern terminus of the line is Taft Avenue at Pasay Rotonda, the intersection between Epifanio de los Santos Avenue (EDSA) and Taft Avenue, while the northern terminus is the North Avenue along EDSA in Barangay Bagong Pag-asa, Quezon City. Three stations serve as connecting stations with the lines of the Manila Light Rail Transit System (LRT) and Philippine National Railways (PNR). The Magallanes station is near PNR's EDSA station, while Araneta Center–Cubao is indirectly connected to the LRT Line 2 station of the same, and Taft Avenue is connected via a covered walkway to the LRT Line 1 EDSA station. No stations are connected to other rapid transit lines within the paid areas, though that is set to change when the North Triangle Common Station, which has interchanges to LRT Line 1 and MRT Line 7, opens in January 2025.

MRT Line 3 stations timeline
Date opened Project Stations
December 15, 1999 Phase 1 North AvenueBuendia
July 20, 2000 AyalaTaft Avenue
January 2025 North Triangle
Legend
Existing terminus
List of stations
Name Distance (km) Connections Location
Between
stations
Total
North Triangle
Interchange with Metro interchange Manila LRT
Interchange with Metro interchange Manila MRT
Quezon City
North Avenue 0.000
  •  1  North Avenue
Quezon Avenue 1.200 1.200
  •  1  Quezon Avenue
  •  6   7   17   34   49  Eton Centris
GMA–Kamuning 1.000 2.200
  •  1  Kamuning
Araneta Center–Cubao 1.900 4.100
Santolan–Annapolis 1.500 5.600
  •  1  Santolan
Ortigas 2.300 7.900
  • 4 EDSA
  •  1  Ortigas
Mandaluyong
Shaw Boulevard 0.800 8.700 none
Boni 1.000 9.700
Guadalupe 0.800 10.500
  •  1  Guadalupe
  • Guadalupe Ferry Station
Makati
Buendia 2.000 12.500
  •  1  Buendia
Ayala 0.950 13.450
  •  1  Ayala
Magallanes 1.200 14.650
Mainline rail interchange  PNR
Taft Avenue 2.050 16.700
  •  1  Tramo
     1  Taft Avenue
Pasay
Stations, lines, and/or other transport connections in italics are either under construction, proposed, unopened, or have been closed.

Operations

[edit]

The line is open from 4:40 a.m. PHT (UTC+8) until 10:10 p.m. on a daily basis.[81] It operates almost every day of the year unless otherwise announced. Special schedules are announced via the public address system in every station and also in newspapers and other mass media. During Holy Week, a public holiday in the Philippines, the line is closed for annual maintenance, owing to fewer commuters and traffic around the metro, leaving the EDSA Carousel as an alternative mode of transport.[82] Normal operation resumes after Easter Sunday.[83] During the Christmas season, operating hours are shortened to allow its staff to celebrate the holidays with their families.[84]

It has experimented with extended opening hours, the first of which included 24-hour operations beginning on June 1, 2009 (primarily aimed at serving call center agents and other workers in the business process outsourcing sector).[85] Citing low ridership figures and financial losses, this was suspended after two days, and operations were instead extended from 5:00 a.m. to 1:00 am.[86] Operations subsequently returned to the former schedule (5:30 a.m. until 11:00 p.m. on weekdays, and 5:30 a.m. until 10:00 pm during weekends and holidays) by April 2010, but services were again extended starting March 10, 2014, with trains running on a trial basis from 4:30 am to 11:30 pm in anticipation of major traffic buildup in light of several major road projects beginning in 2014.[87]

Responding to a commuter's concern on X (formerly Twitter) about the limited operating hours at night,[88] the Department of Transportation (DOTr) explained in August 2023 the need for timely maintenance works, since any delays would affect other portions of the line for the next trips.[89] The DOTr added that unlike the extensive railway systems of Europe and Japan, where 24-hour operations are possible, the MRT system only consists of one line. The department also claimed that if maintenance is not ensured, the line would "slowly deteriorate".[90]

Station facilities, amenities, and services

[edit]
Buendia station, one of the stations with an island platform.
Bridge linking the Taft Avenue station to the nearby EDSA LRT station

Station layout and accessibility

[edit]

The stations have a standard layout, with a platform level and a concourse level.[48] The concourse is usually above the platform, with stairs, escalators and elevators leading down to the platform level.[16] However, fare gates are located at the platform level in most stations, meaning that commuters will need to exit the paid area to catch a train going in the opposite direction. Switching trains without paying a new fare is only possible at the Araneta Center–Cubao, Boni, Buendia, Ayala, and Taft Avenue stations due to their different layout.

The station platforms have a standard length of 130 meters (426 ft 6 in),[48] designed to accommodate trains with four cars.[56] The stations are also designed to occupy the entire span of EDSA, allowing passengers to safely cross between one end of the road and the other.[16]

Most stations are also barrier-free inside and outside the station, and trains have spaces for passengers using wheelchairs.[16] With the exception of Buendia and Ayala stations, and the platform level of Taft Avenue and Boni stations, all stations are situated above ground, taking advantage of EDSA's topology.[91]

Stations either have side platforms, which is the case for most stations, or island platforms, such as Taft Avenue. Due to the very high patronage of the line, before the pandemic, part of the platform corresponding to the first car of the train is cordoned off for the use of senior citizens, pregnant women, children who are below 4 feet (1.2 m) and age seven, and disabled passengers. Since 2021, the first two doors of the first car of the train have been allotted as a priority section for the aforementioned passengers.[92]

The line has a total of 46 escalators and 34 elevators across all 13 stations. Prior to the rehabilitation, only few escalators and elevators were operational. The escalators and elevators were rehabilitated as part of the rehabilitation of the line. The project started in June 2019 and was completed on August 20, 2020.[93]

In February 2012, the line allowed folding bicycles to be brought into trains provided that the wheels do not exceed more than 20 inches (51 cm) in diameter.[94]

Platform screen doors were also planned for each station, with the plans for the platform doors were laid out as early as 2013,[95] however, these plans were delayed until it was reconsidered in 2017.[96]

Shops and services

[edit]

Some stations are connected at concourse level to nearby buildings, such as shopping malls, for easier accessibility. Inside the concourse of all stations are stalls or shops where people can buy food or drinks. Stalls vary by station, and some have fast food stalls.

Since November 19, 2001, in cooperation with the Philippine Daily Inquirer, passengers have been offered copies of the Inquirer Libre, a free, tabloid-size, Tagalog version of the Inquirer, which is available at all stations.[97] In 2014, Pilipino Mirror also started distributing free tabloid newspapers.

Safety and security

[edit]

The line's safety was affirmed in a 2004 World Bank paper prepared by Halcrow, describing the overall state of metro rail transit operations in Manila as being "good".[98] However, since the DOTr took over maintenance of the train system in 2012, the safety and reliability of the system has been questioned, with experts calling it "an accident waiting to happen." While several incidents and accidents were reported between 2012 and 2014, they did not deter commuters from using the system.[99] The Philippine government, meanwhile, continues to assert that the system is safe overall despite those incidents and accidents.[100]

As the line operated significantly above its designed capacity of 350,000 passengers per day from 2004 to 2019,[26] government officials have admitted that capacity and system upgrades are overdue,[101] although the DOTr has never acted on the numerous capacity expansion proposals of the private owners. In the absence of major investment in improving system safety and reliability, DOTr has resorted to experimenting with and implementing other solutions to reduce strain on the system, including crowd management on station platforms[102] and the proposed implementation of peak-hour express train service.[103] However, some of these solutions, such as platform crowd management, are unpopular with passengers.[104]

For safety and security reasons, persons who are visibly intoxicated, insane and/or under the influence of controlled substances, persons carrying flammable materials and/or explosives, and persons carrying bulky objects or items over 1.5 meters (4.9 ft) tall and/or wide are prohibited from entering the line.[105] Products in tin cans are also prohibited on board, citing the possibility of home-made bombs being concealed inside the cans.[106]

In late 2000 and early 2001, in response to the Rizal Day bombings and the September 11 attacks, security was increased. Following a vandalism incident in May 2021,[107] the number of security personnel deployed across all stations was increased and a patrol car was deployed for added security.[108] After a bomb threat incident on September 8, 2023, DOTr formed an inter-agency task force to enhance security across all transportation sectors.[109] Units of the Philippine National Police[110] and security police provided by private companies can be found in all stations. All stations have a head guard. Some stations may also have a deployed K9 bomb-sniffing dog. The line also employs the use of closed-circuit television inside all stations to monitor suspicious activities.

Pets have been allowed to ride since July 12, 2021, but these must be placed inside a carrier bag before boarding a train.[111]

Ridership

[edit]

The original designed ridership of the line is 350,000, yet as the years passed, the number doubled from 450,000 daily passengers in 2006–2007 to 490,000 passengers in 2008 and up to 500,000 passengers from 2010 to 2012, with record numbers reaching as high as 620,000 from 2012 to 2013, before declining to 560,000 in 2014.[27] The high ridership of the line is due to the time consumed when commuting via EDSA, as well as the speed of the trains reaching up to 60 kilometers per hour (37 mph), and connectivity to Metro Manila's major transport hubs, railway lines, and central business districts, which results to a reduced commuting travel time and an increase in ridership. The daily ridership of the line can reach as much as 300,000 to 500,000 passengers from 2012 to 2016, despite poor maintenance and long lines, causing the government to launch bus services, known as MRT Buses, around its stations, to serve as alternatives for 900,000 to 1 million passengers. In addition to the rising daily ridership that continues to exceed the line's designed capacity, and as the government continues to implement the metro line's capacity expansion project, it aims to reach a ridership of 800,000 daily passengers as all of the new trains from China will be added to its current fleet.[43]

Ridership declined in 2015, with a daily average of 327,314 passengers, which is lower than the 2014 record of 464,871 daily passengers on average. It slightly increased in 2016, to 370,036, and the highest recorded daily ridership was recorded at 517,929 in December of that year. However, ridership started to decline by 2017 due to poor maintenance and daily incidents, which continued through 2018 and 2019. A significant drop in ridership was recorded in 2020 due to capacity limitations brought by the COVID-19 pandemic, serving 70,000 to 150,000 passengers daily.[112] It previously served almost 40,000 passengers in June 2020,[113] and 150,000 passengers in January 2021.[114] Until February 2022, the line operated at a limited capacity before capacity limitations were removed by March 1, 2022.

Ridership slightly increased in 2021, servicing 136,935 daily passengers on average due to the increased capacity in November 2021.[115] After the completion of the rehabilitation project in 2022, the line offered free rides to commuters in three months. This, in turn, increased the ridership of the line.[116] By the end of the free rides, a total of 28.6 million passengers rode the line. It also recorded a daily average of 318,055 passengers in the same period.[117] By the end of the year, the line carried 98,330,683 passengers, its highest since the rehabilitation, with an average of 273,141.[118][2]

Statistics

[edit]

Data from the Department of Transportation (DOTr).[112]

Key
Highest recorded ridership
Year Daily average % change Annual ridership % change Highest single-day ridership
1999[f] 23,057 Steady 368,916 Steady 39,760 (December 23, 1999)
2000 109,449 Increase 374.69 39,401,465 Increase 10,580.34 296,969 (December 22, 2000)
2001 250,728 Increase 129.08 90,262,148 Increase 129.08 391,187 (December 14, 2001)
2002 282,993 Increase 12.87 102,443,564 Increase 13.50 417,059 (July 1, 2002)
2003 312,043 Increase 10.27 112,647,474 Increase 9.96 438,809 (December 19, 2003)
2004 338,431 Increase 8.46 122,512,169 Increase 8.76 452,926 (December 16, 2004)
2005 356,673 Increase 5.39 128,758,894 Increase 5.10 465,203 (September 7, 2005)
2006 374,436 Increase 4.98 135,171,387 Increase 4.98 488,733 (December 15, 2006)
2007 395,806 Increase 5.71 142,886,057 Increase 5.71 539,813 (December 21, 2007)
2008 413,220 Increase 4.40 149,585,563 Increase 4.69 527,530 (October 15, 2008)
2009 419,728 Increase 1.57 151,521,764 Increase 1.29 560,637 (September 15, 2009)
2010 424,041 Increase 1.03 153,078,770 Increase 1.03 552,509 (October 15, 2010)
2011 439,906 Increase 3.74 158,806,049 Increase 3.74 577,015 (October 14, 2011)
2012 481,918 Increase 9.55 174,454,146 Increase 9.85 622,880 (August 17, 2012) †
2013 487,696 † Increase 1.20 176,058,278 † Increase 0.92 621,913 (October 25, 2013)
2014 464,871 Decrease 4.68 167,818,336 Decrease 4.68 614,807 (February 14, 2014)
2015 327,314 Decrease 29.59 118,160,484 Decrease 29.59 455,164 (February 25, 2015)
2016 370,036 Increase 13.05 133,952,890 Increase 13.37 517,929 (December 16, 2016)
2017 388,233 Increase 4.92 140,152,161 Increase 4.63 506,001 (February 10, 2017)
2018 289,654 Decrease 25.39 104,275,362 Decrease 25.60 390,325 (January 12, 2018)
2019 270,794 Decrease 6.51 96,932,972 Decrease 7.04 359,447 (January 25, 2019)
2020 121,839 Decrease 55.01 31,799,959 Decrease 67.19 324,803 (January 24, 2020)
2021[115] 136,935 Increase 12.39 45,675,884 Increase 43.64 223,739 (December 23, 2021)
2022 273,141 Increase 99.47 98,330,683 Increase 115.28 389,784 (June 17, 2022)
2023 357,198 Increase 30.77 129,030,158 Increase 31.22 450,298 (August 22, 2023)

Fares and ticketing

[edit]

The line, like all other lines in Metro Manila, uses a distance-based fare structure, with fares ranging from 13 to 28 pesos (24 to 51 U.S. cents), depending on the destination. Commuters who ride the line are charged ₱13 ($0.26) for the first two stations, ₱16 ($0.32) for 3–4 stations, ₱20 ($0.41) for 5–7 stations, ₱24 ($0.49) for 8–10 stations and ₱28 ($0.57) for 11 stations or the entire line. Children below 1.02 meters (3 ft 4 in) (the height of a fare gate) may ride for free.

Fares are free of charge every March 8 (International Women's Day; free rides exclusive for women),[119] June 12 (Independence Day),[120][121] and December 30 (Rizal Day) on limited time slots.[122]

The line, along with the LRT Line 2 and Philippine National Railways lines also offered free rides to students starting July 1, 2019,[123] but students must register to avail a student pass.[124] However, the free rides for students stopped in 2020 due to the COVID-19 pandemic as distance learning was implemented as a mode of learning during the pandemic.[112] With the shift towards the return of physical face-to-face classes, a plan to return the free rides to students by August 2022 was announced;[125] however, free rides for students were only limited to the LRT Line 2 due to more losses that the government will incur as a consequence of the free rides (Line 2 itself later stopped the free rides after three months due to similar reasons).[126] Instead, the line will offer a 20% fare discount for students that wish to avail.[127]

Types of tickets

[edit]
The design of the single journey ticket prior to introduction of Beep card in 2015.

Magnetic tickets (1999–2015)

[edit]

Two types of tickets exist: a single-journey (one-way) ticket whose cost is dependent on the destination, and a stored-value (multiple-use) ticket for 100 pesos. The 200-peso & 500-peso stored-value tickets were issued in the past, but have since been phased out. The single-journey ticket is valid only on the date of purchase. Meanwhile, the stored-value ticket is valid for three months from date of first use.[105]

The tickets come in several incarnations: these include tickets bearing the portraits of former presidents Joseph Estrada and Gloria Macapagal Arroyo,[128] which have since been phased out, and one bearing the logos of the DOTC and the MRTC. Ticket shortages are common: in 2005, the MRTC was forced to recycle tickets bearing Estrada's portrait to address critical ticket shortages, even resorting to borrowing stored-value tickets from the LRTA[129] and even cutting unusable tickets in half for use as manual passes. Shortages were also reported in 2012,[130] and the DOTC was working on procuring additional tickets in 2014.[131] Because of the ticket shortages, it had become common practice for regular passengers to purchase several stored-value tickets at a time, though ticket shortages still persist.[132]

Although it has partnered with private telecommunications companies in experimenting with RFID technology as an alternative ticketing system in the past,[133][134] these were phased out in 2009.[135]

Beep cards (2015–present)

[edit]

Currently, inter-operable beep cards with similar-to-the-previous single-journey and stored-value ticket types are now issued, along with the deployment of brand-new ticketing machines that replaced the barely-used ticketing machines that has been in place since the line's inauguration. The beep, tap-and-go tickets, loadable up to ₱10,000, became available to use in all stations of the line on October 3, 2015.[136]

A shortage of the stored value cards was reported in 2022 due to the global chip shortage caused by the Russian invasion of Ukraine.[137][138]

Fare adjustment

[edit]

Adjusting passenger fares was ordered by President Joseph Estrada as a means to boost flagging ridership figures,[139] and the issue of fares both historically and in the present day continues to be a contentious political issue involving officials at even the highest levels of government.

Current fare levels were set on January 4, 2015, as a consequence of DOTr (formerly DOTC) having to increase fares for LRT Line 1 as per their concession agreement with MPIC-Ayala, with fare hikes delayed for several years despite inflation and rising operating costs.[140] Prior to the current fares levels, fares were set on July 15, 2000, under the orders of then President Estrada; this was intended to have the line become competitive against other modes of transport,[141] but had the effect of causing revenue shortfalls which the government shouldered. While originally set to last only until January 2001,[141] the new fare structure persisted due to strong public opposition against increasing fares,[142] especially as ridership increased significantly after lower fares were implemented.[139] In 2022, when the line waived its fares, ridership also increased.[143] These lower fares—which are only slightly more expensive than jeepney fares—ended up being financed through large government subsidies amounting to around ₱45 per passenger,[142][144] and which for both the MRT and LRT reached ₱75 billion for the 10-year period between 2004 and 2014.[145] Without subsidies, the cost of a single trip is estimated at ₱60,[144] and a ₱10 increase in fares would yield additional monthly revenues of ₱2–3 billion a month.[146]

Passenger fare subsidies are unpopular outside Metro Manila, with subsidy opponents claiming that their taxes are being used to subsidize Metro Manila commuters without any benefit to the countryside, and that the fare subsidies should be used for infrastructure improvements in the rest of the country.[147] In his 2013 State of the Nation Address, President Benigno Aquino III claimed that it would be unfair for non-Metro Manila residents to use their taxes to subsidize the LRT and MRT.[148] However, supporters of the subsidies claimed that the rest of the country benefits economically from efficient transportation in Metro Manila.[149]

In January 2023, a petition was filed for a ₱4–6 fare hike due to a major net loss incurred; in 2022, the incurred revenue was only ₱1.11 billion against expenditures of roughly ₱8.97 billion, resulting in a loss of ₱7.86 billion. In the petition, the MRT-3 management said that fare revenues were never enough to compensate the MRTC to cover the initial investment in the construction, operations, and maintenance of the line.[150] The fare hike is now set for the first quarter of 2024.[151]

Rolling stock

[edit]
MRTC 3000 class
MRTC 3100 class

The line runs light rail vehicles (LRV) in a regular three-car configuration. Four-car trains began operating by March 2022, although most trains remain running in three cars.[54] The DOTr planned to convert all three-car trains to four-car trains by 2023.[56] Two train types run in the line, the latest being those purchased from CRRC Dalian, under the Aquino administration.

The line has a total of 121 light rail vehicles. 73 of which were made in the Czech Republic by ČKD (now part of Siemens AG)[1] and were purchased with export financing from the Czech government.[152] One ČKD train car was damaged following a derailment of a train in 2014. Another 48 were made by CRRC Dalian in China that were purchased at a cost of ₱3.8 billion. Trains have a capacity of 1,182 passengers,[1] expandable to 1,576,[153] which is a little bigger than the normal capacity of LRT Line 1 first generation rolling stock that has a capacity with the same configuration of 1,122 passengers, although trains came with air conditioning.[g] Despite this, it is designed to carry in excess of 23,000 passengers per hour per direction (PPHPD), and is expandable to accommodate 48,000 passengers per hour per direction.[1]

The plans for new rolling stock has been an issue for the MRT during the Aquino administration under DOTC's leadership of then Secretary Joseph Emilio Abaya, with plans to acquire 52-second-hand LRVs offered from Madrid Metro in Spain with a budget of ₱8.43 billion,[154] along with a proposal from Inekon Trams in 2013.[155] However, undisclosed issues and train incompatibility issues regarding the project, the project was downgraded to 48 LRVs, with the contract having CRRC Dalian supply 48 new LRVs. The deployment of the Dalian trains was delayed due to several factors, including weight limits on existing tracks and inconsistencies in production, which has since been corrected. On October 27, 2018, DOTr started the gradual deployment of the 2nd-generation trains.[47] Currently, none of the Dalian trains are in operation as a consequence of restrictions imposed by the line's current maintenance provider, Sumitomo Corporation.[115]

The trains are designed to run at a maximum speed of 65 kilometers per hour (40 mph), but currently run at an operating speed of 60 kilometers per hour (37 mph), though some areas are limited to 40 km/h (25 mph) like turnouts.

The Passenger Assist Railway Display System (PARDS), a passenger information system powered by LCD screens installed near the ceiling of the train that shows news, advertisements, current train location, arrivals and station layouts, are already installed inside the first-generation trains. PARDS is also installed on trains on LRT lines 1 and 2.[156]

Depot

[edit]

The line maintains an underground depot in Quezon City near North Avenue station. Above the depot is TriNoma, a shopping mall owned by the Ayala Corporation. The depot occupies 84,444 square meters (908,950 sq ft; 8.4444 ha) of space and serves as the center of operations and maintenance. It is connected to the mainline through a spur line. The depot is capable of storing 81 light rail vehicles, with the option to expand to include 40 more vehicles as demand arises.[48] They are parked on nine sets of tracks, which converge onto the spur route and later on to the main network.[1] However, a lot of rail tracks for storage inside the depot owned by MRTC were taken by DOTC (now DOTr) to repair broken rails,[157] as DOTC's previous maintenance provider did not purchase spare rails. These rails have since been replaced during the rehabilitation done along the entire line by Sumitomo.

Other infrastructure

[edit]

Signaling

[edit]
Two-aspect signal lights at Quezon Avenue station

The line uses the CITYFLO 250 fixed block signaling solution supplied by Alstom (formerly Bombardier Transportation),[158] designed for light rapid transit operations with on-board automatic train protection (ATP) system on trains.[159][160] Other components include train detection using track circuits, EBI Screen 900 centralized traffic control, and computer-based interlocking.[161][1]

Adtranz, later Bombardier Transportation, designed and supplied the original signaling system and maintained it from 2000 to 2012.[158][162] The firm owns the proprietary rights to supply new components for the system. In October 2015, Bombardier was awarded the contract to upgrade the system's local control system. The seven-month upgrade replaced the MAN 900 local control system with the newer EBI Screen 900 system with modern computers and fiber optic technology.[163]

The previous maintenance providers failed to properly maintain the signaling system and used non-original spare parts to save costs. This in turn, caused many problems within the system which became among the top three causes of frequent service interruptions.[158] On February 9, 2018, the Department of Transportation (DOTr) signed a memorandum of understanding (MoU) with original equipment manufacturer Bombardier Transportation to upgrade the system and procure the spare parts.[158] Included in the MoU was a two-year maintenance contract[158] that was later cancelled in May 2019 due to the rehabilitation program which included the maintenance of the signaling system by Sumitomo.[164]

The 2019–2021 upgrade covered the replacement of copper cables with fiber optic cables,[165] installation of 71 new signal lights,[166] new interlocking equipment, new point machines, new track circuits (including tuning units which form part of the circuits),[167] and other wayside equipment.[168] Works continued during the acquisition of Bombardier Transportation by Alstom in January 2021. The upgraded system was commissioned on October 24, 2021.[169]

Tracks

[edit]
Turnout and new railway sleepers near Taft Avenue station

The standard gauge tracks consist of 54-kilogram-per-meter (36 lb/ft) rails designed to the UIC 54 rail profile,[1][4] which are welded together to form a continuous welded rail.[57] Some rails located at turnouts have fishplates bolted at the ends of the rail. These are laid on sections of the line with ballasted and concrete plinth sections.[48] Sections with track ballast are located on at-grade sections and the underground portion of the line (except Buendia and the turnouts south of the station), while plinth sections are located at elevated sections of the line. The tracks on ballasted sections are supported by concrete sleepers.[48] The rehabilitation of the line led to the introduction of fiber-reinforced foam urethane (FFU) railway sleepers. FFU sleepers are found at the depot and the turnouts near Taft Avenue station.[170]

Plans to replace the rail tracks were laid in 2015. Replacement works in certain sections of the line were conducted in February and March of that year.[171][172] In January 2015, the joint venture of Jorgman, Daewoo, and MBTech Group was awarded the ₱61.5 million contract for the major replacement works. The joint venture supplied 7,296 pieces of 12-meter (39 ft) rails.[173]

By 2014, speed restrictions were imposed due to safety concerns, which downgraded the operating speed from 60 km/h (37 mph) later downgraded to 40 km/h (25 mph),[174] subsequently downgraded to 30 km/h (19 mph).[175] A comprehensive rail replacement program started on November 4, 2019, under Sumitomo's maintenance.[57] 4,053 pieces of 18-meter (59 ft) rails assembled by Nippon Steel Corporation in Fukuoka were used for the replacement program.[176] Rail replacement works were initially suspended during the enhanced community quarantine in Luzon, but works resumed in April 2020 and the replacement was fast-tracked.[177][178] The replacement program was slated to be completed by February 2021, but was completed five months early, in September 2020.[178] The turnouts near Taft Avenue station were repaired in October and November 2020.[179][180] The rail replacement was intended to increase the operating speed back to 60 km/h (37 mph) and was achieved on December 7, 2020.[181]

Plans and proposals

[edit]

Privatization

[edit]

In November 2022, the Department of Transportation said that it is considering to privatize the operations and maintenance of the line to enhance efficiency, reduce operating costs, and keep fares affordable. The rail lines assets will remain owned by the government, similar to the LRT Line 1.[182] Such a plan was announced as early as 2017.[183]

Line merge with LRT Line 1

[edit]

Although Phase 1 of the line (Taft Avenue to North Avenue) has already been built, the original route envisioned by the government was for it to traverse most of EDSA (from Monumento to Taft Avenue), eventually meeting with the LRT Line 1 at Monumento in Caloocan (Phase 2) to create a seamless rail loop around Metro Manila. The total length of the planned extension was 5 kilometers (3.1 mi).

A study about the integration of Metro Manila's railway network, published by JICA in 2001, proposes the through-operation of both LRT-1 and the MRT-3, which would have interoperability to create a seamless loop around the region. The trains would start from Monumento before turning back to the mainline of LRT 1 at Pasay Rotonda.[184][185]

The expansion was shelved by then President Gloria Macapagal Arroyo in favor of the LRT Line 1's extension from Monumento to a new common station that it will share with at North Avenue, thus closing the loop. The National Economic and Development Authority, as well as President Arroyo have said that the link at North Avenue is a national priority, since it would not only provide seamless service between the LRT Line 1 and MRT Line 3 but would also help decongest Metro Manila.[186] It is estimated that by 2010, when the extension is completed, some 684,000 commuters would use the line every day from the present 400,000, and traffic congestion on EDSA would be cut by as much as 50%.[187]

Proposals to fully unite LRT-1 and MRT-3 operations and systems have been pitched but has not been pursued so far. Feasibility tests for this proposition included LRT-1 trains visiting MRT 3 depot facilities and running them on the entire line. Even if the structure gauge connecting the two rail lines has been successfully tested,[188] commuters have to go down at Fernando Poe Jr. station of LRT Line 1 and walk over or take a tricycle or jeepney for the 1-kilometer (0.62 mi) distance to the North Avenue station of MRT Line 3.[189] In 2011, the Department of Transportation and Communications (precursor to the DOTr), under Transportation Secretary Jose de Jesus, launched an auction for a temporary five-year operations and maintenance contract for the two lines; the bidding was set for July. Over twenty-four companies expressed interest to bid which included Ayala Corporation, Bombardier Transportation, CAF, Metro Pacific, Sumitomo Corporation, Siemens, DMCI Holdings, San Miguel Corporation, and others.[190] De Jesus later resigned from the DOTC in June for personal reasons,[191] and his successor, Mar Roxas, halted the auction process and was later shelved.[192]

The proposal to integrate the LRT Line 1 and MRT Line 3 was revived in June 2024 by Metro Pacific Investments. The company, which holds a majority stake in LRT Line 1 operator Light Rail Manila Corporation, submitted an unsolicited proposal to integrate the operations of the two lines.[193] It is now under review by DOTr and has been endorsed to the former by the PPP Center, after initially rejecting it due to being incomplete in substance. The proposed line merger will run both LRT-1 and MRT-3 trains on the same track, while resolving outstanding issues such as the Dalian trains, supply chain and potential line expansion.[194]

Southern and western extension

[edit]

In the 1999 Metro Manila Urban Transportation Integration Study, the line was proposed to extend all the way to Navotas, which is only 10 kilometers (6.2 mi), and another one to the reclamation area (known as Bay City) in about 2 kilometers (1.2 mi). The line was also intended to extend all the way to Kawit.[195]

In a feasibility study in 2009 and in 2015, launched by Japan International Cooperation Agency, along with the Department of Transportation, the Transport and Traffic Planners (TTPI) Inc.[196] and other Japanese and local railway officials, launched a plan to extend the present MRT line's southern end, by constructing a 2.2-kilometer (1.4 mi) at-grade and underground segment, from Taft Avenue station to the SM Mall of Asia complex.[197] Plans were also laid out to add another station, by traversing through Macapagal Boulevard and linking the line to the Parañaque Integrated Terminal Exchange, therefore adding another 3.1 kilometers (1.9 mi) to the main line. The study also included a planned 7.2-kilometer (4.5 mi) extension to the northern and western cities of Navotas, Southern Caloocan, and Malabon, which is also included to the planned merging project with the LRT Line 1, and connecting it to the North–South Commuter Railway.[197]

Due to the numerous problems surrounding the project, such as right-of-way and cost issues, the government decided to presumably scrap the extension plans, and look for alternatives instead, such as the planned Integrated Pasay Monorail project by the Pasay City LGU and SM Investments, starting from the Taft Avenue station to SM Mall of Asia.[198]

Makati Loop

[edit]

In the initial stages of the construction of the transit line, a proposal was formulated for a supplementary rail extension that would traverse from Buendia to Gil Puyat stations, situated between Ayala and Buendia stations. The sole existing trace of this discontinued proposal is an underground tunnel extending from Buendia to Ayala stations, taking a rightward trajectory towards Ayala Avenue, before running towards Gil Puyat Avenue.[199] Despite sporadic references, there is presently no intention to reassess or reinstate this abandoned initiative.

Extension to NAIA

[edit]

In 2000, during the completion of the line, MRTC proposed an idea to build the extension of the line to Ninoy Aquino International Airport (NAIA), running from Taft Avenue station, then passing along Roxas Boulevard, and ending at this airport. The project was expected to cost ₱500 million.[200][199]

Transfer of operations from MRTC to LRTA

[edit]

A new study for the Metro Manila Rail Network has been unveiled by DOTC Undersecretary for Public Information Dante Velasco that LRT 1, LRT 2, and MRT 3 will be placed under the management of the Light Rail Transit Authority (LRTA). This is due to maintenance cost issues for LRT 1's maintenance cost, which is approximately ₱35 million, along with LRT Line 2's ₱25 million and MRT Line 3's ₱54 million maintenance costs. Another reason for this study is for the unification of the lines. According to DOTC Undersecretary for Rails Glicerio Sicat, the transfer was set by the government in June 2011.[201] However, it is unlikely that the private owners, MRTC, will approve this plan.

On January 13, 2011, LRTA Administrator Rafael S. Rodriguez took over as officer-in-charge of the line in preparation for the integration of operations of the three lines,[202] but with the entry of a new leadership into the DOTC that year and in 2012, the transfer was deemed not likely to happen; however, in April 2012, a LRT 1 trainset made the first trial journey to the MRT 3 depot.[203]

On May 26, 2014, the line's general manager Al Vitangcol was replaced by LRTA Administrator Honorito Chaneco as officer-in-charge. The move came after Vitangcol was accused by the ambassador of the Czech Republic of extortion and for awarding the maintenance contract in October 2012 to PH Trams, a company established by Vitangcol's uncle-in-law. Vitangcol was also involved in an attempt to extort $30 million from Inekon Group in exchange of 48 train vehicles in July 2012.[204]

As the build-lease-transfer contract of the DOTr and MRTC nears its 2025 expiration, the department plans to transfer its management of the line to the LRTA. Such a plan was pitched in July 2023 by Transportation Undersecretary for Railways Cesar Chavez, when the department considered privatizing the operations and maintenance and bundling it with that of the LRT Line 2.[205]

North Triangle Common Station

[edit]

On November 21, 2013, the NEDA board, chaired by President Benigno Aquino III, approved the construction of a common station within North Avenue between SM City North EDSA and TriNoma shopping malls. It is estimated to cost ₱1.4 billion. It will feature head-to-head platforms for LRT 1 and MRT 3 trains with a 147.4-meter (484 ft) elevated walkalator to MRT 7.[206] SM Investments Corporation posted 200 million pesos for the naming rights of the common station.[207] This is inconsistent with the original plan of having seamless connectivity to Monumento and is also an unusual arrangement of having two train stations beside each other. However, the project was shelved indefinitely due to disputes over cost, engineering issues and naming rights.[208] The Supreme Court halted the construction of the project in August 2014 after SM Prime Holdings contested the new location near Trinoma.[209][210] An agreement was later reached under the administration of President Rodrigo Duterte on September 28, 2016, and the common station finally begun construction on September 29, 2017.[211] The station will open in 2025.[212]

Incidents

[edit]
Passengers unloading from a 3000 class train in 2014 due to a service incident.

During the testing period of the system, the MRT–3 has been prone to numerous disruptions and breakdowns due to technical problems in the overall systems and design since its opening in 1999, due to many factors, such as the humid conditions in the country, lack of accessibility to the stations, and incompatible problems in the rolling stock, causing major adjustments to the system.

However, problems began to arise in 2012, due to poor maintenance causing train glitches, lack of spare parts, and negligence. The system has faced numerous interruptions and accidents. This in turn has caused lower ridership, frequent unloading of passengers and passenger inconvenience.[213]

Among the notable incidents involving the railway line are:

  • On January 10, 2000, full line operations were suspended after a fire broke out at the former bus depot of the Metro Manila Transit Corporation in the vicinity of the MRT-3 depot. The fire damaged one of its overhead electric lines and disabled one of two access tracks to the depot.[214]
  • On October 23, 2000, a flood at the EDSA-Taft intersection and an ongoing construction project that obstructed the sidewalk led to overcrowding at Taft Avenue station and left hundreds of passengers stranded.[215]
  • On March 19, 2003, a vagrant was killed by a northbound train after climbing onto the tracks near the Santolan-Annapolis station. The incident caused train operations to be suspended for half an hour.[216]
  • On August 29, 2003, a vagrant and a jeepney barker climbed up a MRT post near Cubao station. Both of them fell to their deaths after a brief altercation.[217]
  • On March 11, 2004, security guards of the MRT-3 staged a strike in protest of delayed salaries and other withheld benefits. To maintain station security during the disruption, the National Capital Region Police Office deployed officers to MRT-3 stations. In response to the strike, the DOTC ordered the termination of the security agency's contract.[218]
  • On May 20, 2004, heavy rains and strong winds caused a billboard to fall from a building in Cubao, which was carried towards the MRT tracks. Operations were temporarily suspended for an hour until the tracks were cleared of debris.[219]
  • On August 12, 2004, southbound operations were temporarily suspended after an overhead power cable snapped and triggered a small explosion at GMA-Kamuning station.[220]
  • On July 6, 2005, a MRT train hit and killed a security guard who was searching for thieves near the tracks at Guadalupe station, causing temporary disruption to train operations. It was determined that the guard was not wearing reflectors and was outside the designated safe zone for maintenance and security personnel.[221]
  • On September 23, 2005, strong winds caused a billboard to fall on the MRT power lines near Cubao station. The billboard was also dragged by a northbound train leaving Cubao and caused the last car to catch fire. As a result, train operations were limited to between the Taft Avenue and Shaw Boulevard stations. The incident has also caused the Metropolitan Manila Development Authority to call on local government units to strictly regulate billboards being put up along major roads.[222]
  • On October 22, 2006, a man was run over by a northbound MRT train between the Santolan and Ortigas stations. Reports say that the victim was believed to be a rugby boy and may have jumped from a nearby flyover. As a result, train operations were suspended for 10 minutes.[223]
  • In August 2010, a billboard dismantling operation at the Ortigas station of the Manila MRT-3 resulted in an accident when steel debris fell onto the overhead wires, disrupting train services. The debris also damaged multiple vehicles and caused significant traffic congestion on EDSA below.[224]
  • On August 18, 2012, a man sexually assaulted a female cashier passing through Santolan-Annapolis station, prompting an investigation from the Quezon City Police District.[225]
  • On November 3, 2012, a MRTC 3000 class train from the Araneta Center-Cubao station caught fire as it approached GMA–Kamuning station, causing passengers to scramble to the exits, and having two women injured. The train caught fire due to electrical short-circuit technical failure.[226]
  • On May 8, 2013, a man was killed in an apparent suicide after allegedly jumping in front of an oncoming MRTC 3000 class train at Guadalupe station.[227]
  • On March 26, 2014, a southbound MRTC 3000 class train at Guadalupe station suddenly stopped due to the train driver not observing the red light status at the Guadalupe station and accelerated southbound without getting prior clearance from the Control Center, causing the automatic train protection system to trigger and activate the emergency brakes, resulting in eight injuries.[228]
  • On August 13, 2014, a southbound MRTC 3000 class train heading to Taft Avenue station derailed and overshot to the streets. The train first stopped after leaving Magallanes station due to a technical problem. Later on, the train broke down altogether, so another train was used to push the stalled train. During this process, however, the first train became detached from the rails and overshot towards Taft Avenue. As a result, the train crashed through the buffer stop and concrete barriers and derailed onto Taft Avenue. At least 38 people were injured. The accident was blamed on two train drivers and two control personnel for failing to follow the proper coordination procedures and protocol.[229][230]
  • On September 2, 2014, a MRTC 3000 class train continued with one of its doors left open after a train door failed to close at the Guadalupe station. The passengers were then evacuated after the train arrived at Boni station.[231]
  • On November 14, 2017, an alighting passenger at the Ayala station suddenly fell down to the tracks. The passenger was caught between the first and second cars of the train, and her arm was cut off. Operations were disrupted but was resumed shortly.[232] The injured passenger was then brought to a nearby hospital and her arm was reconnected by surgeons the following day.[233] Following this incident, the government reconsidered the use of platform screen doors in stations to prevent such incident.[96]
  • On November 16, 2017, at 11:30 am, at least 140 passengers were evacuated from a train car that detached from a MRTC 3000 class train between the railway lines of Buendia and Ayala Avenue Stations.[234]
  • On August 7, 2018, an aircon leak caused the inside of a MRTC 3000 class train to flood, prompting passengers inside to open their umbrellas. The train was removed from service to fix the air conditioning unit and the train involved in the incident returned to service the following day.[235]
  • On September 26, 2018, two maintenance vehicles collided between Buendia and Guadalupe stations while doing a routine track maintenance, injuring 7 people. This resulted in a one-hour delay of the deployment of trains, causing long lines at stations.[236]
  • On September 6, 2019, an overhead catenary line section snapped at Guadalupe station, causing a power supply glitch in the whole line affecting over 7,000 passengers. Partial operations were implemented from North Avenue station to Shaw Boulevard station. The situation normalized at 5:00 pm.[237] The incident was caused by a defective and old Protection and Control Unit (PTU) that was overdue for replacement, after an investigation was made. Train preparation and daily maintenance were among the factors that failed to prevent this incident.[238]
  • On November 4, 2019, at 4:08 pm, a MRTC 3000 class train suddenly emitted smoke while on the northbound track of the line. Around 530 passengers were unloaded. Around two hours after the incident, the operation of the line was back to normal.[239] The fire was caused by a short-circuit in the traction motor.[240]
  • On May 9, 2021, two men were arrested for illegally going down to the railway tracks at Quezon Avenue station to take a selfie.[241]
  • On May 12, 2021, a MRTC 3000 class train car was vandalized near Taft Avenue station. An investigation found that an unidentified culprit had cut the perimeter fence near the station, which may have caused the vandalism.[107]
  • On October 9, 2021, a MRTC 3000 class train car caught fire near the Guadalupe station. A provisional service was implemented between North Avenue and Shaw Boulevard station, and the site of the incident was declared fire out at 9:51 pm. As a result of the incident, 8 passengers sustained minor injuries.[242] Normal operations resumed the following day.[243]
  • On November 21, 2021, a window in a MRTC 3000 class LRV was damaged due to a stoning incident, with one injury reported.[244] The suspect was later identified as a garbage collector and was subsequently arrested and charged.[245]
  • On June 12, 2022, two persons fell to their deaths from the EDSA-Taft Avenue (Tramo) flyover, onto the MRT-3 tracks leading to Taft Avenue station, causing an hour-long interruption in services.[246]

Notes

[edit]
  1. ^ a b TES Philippines Inc. is the Philippine subsidiary of Mitsubishi Heavy Industries.
  2. ^ Philippine Trans Rail Management and Services Corporation
  3. ^ Through its Maintenance Transition Team
  4. ^ Maintaining the line until July 31, 2025, pursuant to its contract with the DOTr.
  5. ^ The overhauls were carried out during most of the entire duration of the contract (originally 43 months) and not the initial 26-month rehabilitation period.
  6. ^ Data from December 16 to 31, 1999.
  7. ^ The LRT Line 1 first-generation trains originally came with forced ventilation until the trains were refurbished with air conditioning from 2003 to 2004.

References

[edit]
  1. ^ a b c d e f g h i j k l m n o "About". Metro Rail Transit. Archived from the original on January 14, 2022. Retrieved March 5, 2022.
  2. ^ a b c "MRT-3 served around 357K passengers a day in 2023: DOTr". ABS-CBN News. January 3, 2024. Retrieved January 3, 2024.
  3. ^ Japan International Cooperation Agency; Oriental Consultants Co., Ltd.; ALMEC Corporation; Katahira & Engineers International; Tonichi Engineering Consultants, Inc. (July 2013). APPENDICES (PDF). STUDY ON RAILWAY STRATEGY FOR ENHANCEMENT OF RAILWAY NETWORK SYSTEM IN METRO MANILA OF THE REPUBLIC OF THE PHILIPPINES - FINAL REPORT - LRT LINE 1 CAVITE EXTENSION PROJECT (Report). Vol. 1. Retrieved February 27, 2022.
  4. ^ a b c Department of Transportation and Communications (2013). Design and/or Supply and Delivery of Forty-Eight (48) Light Rail Vehicles with On-board Communication System (Radio, Public Address, Intercom), On-board ATP System and One (1) Unit Train Simulator (PDF) (Report). Archived (PDF) from the original on December 22, 2021. Retrieved December 22, 2021.
  5. ^ "Govt eyes June for start of MRT-LRT loop project". BusinessWorld. April 18, 2008. Retrieved April 5, 2022 – via GMA News.
  6. ^ Dela Cruz, Raymond Carl (September 10, 2024). "Bongon, Miranda named MRT-3, PNR general managers". Philippine News Agency. Retrieved September 13, 2024.
  7. ^ Times, The Manila (January 10, 2024). "DoTr to roll out MRT-3, LRT-2 bidding this year". The Manila Times. Retrieved June 8, 2024.
  8. ^ Cabato, Luisa (January 3, 2024). "MRT-3 ridership increased by 30% in 2023, says official". INQUIRER.net. Retrieved June 8, 2024.
  9. ^ a b c Jose, Ricardo; Mabazza, Daniel; Lagman, Marco Stefan; Villasper, Jonathan. "Planning Metro Manila's Mass Transit System" (PDF). University of the Philippines Diliman. Archived from the original (PDF) on April 20, 2017. Retrieved February 19, 2022.
  10. ^ "Light Rail Transit Authority Company History". Light Rail Transit Authority. Archived from the original on September 24, 2014. Retrieved September 13, 2014.
  11. ^ a b c d e "G.R. No. 114222". April 6, 1995. Archived from the original on February 23, 2018. Retrieved November 19, 2021.Public Domain This article incorporates text from this source, which is in the public domain.
  12. ^ a b c d "Metro Rail Transit Corporation". www.mrt3.com. Retrieved June 17, 2024.
  13. ^ "Ramos inaugurates EDSA rail system". Manila Standard. May 6, 1993. p. 19.
  14. ^ a b "Levin blames Tatad for delay of LRT-3". Manila Standard. March 17, 1994. p. 17.
  15. ^ a b Macaspac, Joem H.; Garcia, Ma. Luisa M. (March 28, 1996). "First phase of Edsa metro rail transit system under way". Manila Standard. Kamahalan Publishing Corporation. Retrieved January 21, 2014 – via Google News Archive.
  16. ^ a b c d e Anonas, Alma S. (June 10, 1999). "On track and heading for Year 2K on MRT-3". Manila Standard. Kamahalan Publishing Corporation. Retrieved January 21, 2014 – via Google News Archive.
  17. ^ "About Us". Metro Rail Transit Corporation. Retrieved May 26, 2022.
  18. ^ Marcelo, Elizabeth (January 14, 2016). "DOTC at fault for 'inefficient' maintenance providers, letting MRTC off the hook —COA". GMA News. Retrieved December 10, 2021.
  19. ^ "Miracle rail project to rid Edsa of jams". New Straits Times. The New Straits Times Press (M) Bhd. December 15, 1999. Retrieved January 21, 2014 – via Google News Archive.
  20. ^ "MRT 3 Fully Completed; Inauguration, Turnover Set on July 20". Manila Bulletin. Manila Bulletin Publishing Corporation. July 16, 2000. Archived from the original on July 13, 2021.
  21. ^ Trinidad, Andrea H. (January 2, 2000). "Metrostar Express proves a big disappointment". Philippine Daily Inquirer. Retrieved January 21, 2014 – via Google News Archive.
  22. ^ Rivera, Blanche S. (January 13, 2000). "Metro trains on EDSA running almost empty". Philippine Daily Inquirer. Retrieved January 21, 2014 – via Google News Archive.
  23. ^ Katigbak, J.R. (January 8, 2000). "New white elephants in Metro Manila". Philippine Daily Inquirer. Retrieved January 21, 2014 – via Google News Archive.
  24. ^ Zurbano, Joel (May 1, 2000). "Officials could face graft raps over MRT-3". Manila Standard. Vol. 14, no. 442. p. 95. Retrieved February 27, 2024.
  25. ^ a b Dela Paz, Chrisee (August 28, 2017). "Busan Universal Rail calls DOTr's move to end contract 'unfair'". Rappler. Retrieved November 21, 2017.
  26. ^ a b Amojelar, Darwin G. (August 14, 2014). "DERAILED | 5 things you should know about MRT3 and the mess it's in". InterAksyon. TV5 News and Information. Archived from the original on August 16, 2014. Retrieved August 17, 2014.
  27. ^ a b de Fiesta, Ria (February 27, 2014). "Abaya: MRT-3 operating at overcapacity". ABS-CBN News and Current Affairs. Retrieved August 17, 2014.
  28. ^ Tiglao, Rigoberto (October 5, 2014). "MRT-3 may collapse anytime". The Manila Times. Retrieved April 4, 2022.
  29. ^ Arcangel, Xianne (November 25, 2016). "Vitangcol faces graft raps over alleged extort try on Czech firm". GMA News. GMA Network Inc. Retrieved January 11, 2022.
  30. ^ "APT wins MRT-3 maintenance contract". Rappler. September 2, 2013. Retrieved January 11, 2022.
  31. ^ Cruz, Neal H. (September 3, 2014). "DOTC at fault for MRT-3 breakdowns". Philippine Daily Inquirer. Retrieved January 16, 2022.
  32. ^ Rosario, Ben (October 14, 2014). "House committee to investigate MRT3 controversies". Manila Bulletin. Archived from the original on February 5, 2016. Retrieved January 30, 2016.
  33. ^ Estanislao, Anna (February 4, 2016). "Abaya, DOTC officials 'may have violated' anti-graft law over MRT-3". CNN Philippines. Archived from the original on February 5, 2016. Retrieved February 5, 2016.
  34. ^ De Guzman, Kristine (February 4, 2016). "DOTC chief shrugs off Senate report on MRT3". CNN Philippines. Archived from the original on February 5, 2016. Retrieved February 5, 2016.
  35. ^ "Bidding for MRT3 maintenance contract fails". Rappler. October 29, 2014. Retrieved January 11, 2022.
  36. ^ Bondoc, Jarius (January 26, 2015). "LRT, MRT biddings all flop – as planned". The Philippine Star. Retrieved January 11, 2022.
  37. ^ Mariano, Keith Richard (September 2, 2015). "DOTC starts 'emergency' procurement of MRT-3 maintenance contract". GMA News. Retrieved January 10, 2022.
  38. ^ "MRT rolling stock, signaling system maintenance begins". Department of Transportation and Communications. January 8, 2016. Retrieved January 13, 2022 – via the Official Gazette of the Republic of the Philippines.
  39. ^ Marasigan, Lorenz (July 27, 2017). "MRT 3 flawed from the start–Busan". BusinessMirror. Retrieved November 21, 2017.
  40. ^ "DOTr: Gov't to take over MRT3 maintenance". CNN Philippines. November 6, 2017. Archived from the original on November 9, 2017. Retrieved November 21, 2017.
  41. ^ a b c Regalado, Pia (May 31, 2023). "MRT's Four-Car Trains Are Coming Soon to Accommodate More Passengers". spot.ph. Retrieved May 31, 2023.
  42. ^ JICAChannel02 (June 10, 2014). "(The Philippines) MEGA MANILA INFRASTRUCTURE ROADMAP (Long Ver.)". YouTube. Archived from the original on December 13, 2021. Retrieved April 20, 2016.{{cite web}}: CS1 maint: numeric names: authors list (link)
  43. ^ a b "More MRT-3 coaches on the way". Official Gazette of the Republic of the Philippines. January 18, 2016. Retrieved April 20, 2016.
  44. ^ Francisco, Kevin Bruce (May 7, 2016). "New MRT Line 3 coaches begin operations today". YugaTech. Retrieved May 5, 2022.
  45. ^ "Dalian to pay cost of adjustments of unused MRT3 trains —Tugade". GMA News Online. July 8, 2018. Retrieved September 25, 2018.
  46. ^ Rey, Aika (August 30, 2018). "Chinese firm Dalian agrees to pay all costs to fix unused MRT3 trains". Rappler.
  47. ^ a b Talabong, Rambo (October 27, 2018). "After years of delay, DOTr begins adding Dalian trains to MRT3". Rappler. Retrieved March 15, 2022.
  48. ^ a b c d e f g Procurement of MRT3 Capacity Expansion Project Lot 2: Upgrade of Ancillary Systems (PDF) (Report). 2016. Archived (PDF) from the original on November 9, 2021. Retrieved January 12, 2022.
  49. ^ "DOTC opens bidding for P836-M MRT-3 ancillary systems". Department of Transportation and Communications. May 21, 2014. Retrieved May 3, 2022 – via Official Gazette of the Republic of the Philippines.
  50. ^ Balinbin, Arjay L. (March 9, 2022). "MRT-3 testing four-car configuration to expand capacity". BusinessWorld. Retrieved March 9, 2022.
  51. ^ Ramirez, Robertzon (January 28, 2016). "MRT-3 new trains may not run efficiently – expert". The Philippine Star. Retrieved May 5, 2022.
  52. ^ Lo, Francis Christopher (May 30, 2016). MRT3 Dalian 8MLB 4-Car Train. YouTube. Retrieved March 9, 2022.
  53. ^ Dela Cruz, Raymond Carl (March 11, 2022). "MRT eyes 4-car train setup after successful 'dynamic testing'". Philippine News Agency. Retrieved March 28, 2022.
  54. ^ a b Recuenco, Aaron (March 28, 2022). "MRT-3 starts month-long free ride, deploys 4-car train set". Manila Bulletin. Archived from the original on March 28, 2022. Retrieved March 28, 2022.
  55. ^ Dela Cruz, Raymond Carl (April 18, 2022). "MRT-3 rolls out another 4-car train after Holy Week shutdown". Philippine News Agency. Retrieved April 18, 2022.
  56. ^ a b c Manahan, Job (March 29, 2022). "MRT-3 eyes 4-car configuration for all trains next year: official". ABS-CBN News. Retrieved March 30, 2022.
  57. ^ a b c Mercurio, Richmond (January 12, 2020). "MRT-3 rail replacement complete by 2021". The Philippine Star. Retrieved April 8, 2022.
  58. ^ Dela Paz, Chrisee J. V. (December 17, 2014). "Sumitomo, Sobrepeña to tap ally Metro Pacific for MRT-3 upgrade". BusinessWorld. Retrieved April 11, 2022.
  59. ^ Desiderio, Louella (June 4, 2017). "SMC interested in MRT-3 rehab". The Philippine Star. Retrieved April 11, 2022.
  60. ^ "DOTr studying private owner's offer to maintain MRT-3". CNN Philippines. November 25, 2017 [November 17, 2017]. Archived from the original on April 11, 2022. Retrieved April 11, 2022.
  61. ^ Layug, Margaret Claire (November 29, 2017). "DOTr: Sumitomo, Mitsubishi back as MRT3 maintenance providers starting 2018". GMA News. Retrieved April 24, 2022.
  62. ^ a b Padin, Mary Grace (November 8, 2018). "Government, inks P18.8 billion JICA loan for MRT-3 rehabilitation". The Philippine Star. Retrieved January 10, 2022.
  63. ^ Lao, Joshua (August 18, 2018). "NEDA approves MRT3 rehab". Daily Tribune. Archived from the original on June 2, 2022. Retrieved April 24, 2022.
  64. ^ a b Subingsubing, Krixia (December 29, 2018). "Sumitomo back on track with MRT 3". Philippine Daily Inquirer. Retrieved January 2, 2019.
  65. ^ Subingsubing, Krixia (January 3, 2019). "3-year MRT 3 rehab to start this month". Philippine Daily Inquirer. Retrieved March 31, 2022.
  66. ^ Mendez, Christina (March 7, 2019). "'Reenacted budget to affect MRT-3 rehab, subway project'". The Philippine Star. Retrieved March 31, 2022.
  67. ^ Orellana, Faye (March 6, 2019). "MRT-3 rehab kickoff moved to May". Philippine Daily Inquirer. Retrieved March 31, 2022.
  68. ^ Magsino, Dona (May 1, 2019). "MRT3 rehab, maintenance starts". GMA News Online. Retrieved June 16, 2021.
  69. ^ a b c d "MHIENG Completes Rehabilitation of Manila's MRT-3 Rail Line". Tokyo: Mitsubishi Heavy Industries. March 24, 2022. Retrieved March 31, 2022.
  70. ^ Marquez, Consuelo (November 8, 2018). "PH, Japan sign loan agreement for 26-month MRT-3 rehab". Philippine Daily Inquirer. Retrieved March 31, 2022.
  71. ^ Amojelar, Darwin (December 31, 2018). "Sumitomo asked to start MRT 3 rehabilitation in '19". Manila Standard. Retrieved January 2, 2019.
  72. ^ Rita, Joviland (June 24, 2020). "Limited work force, experts affected MRT3 rehab work during ECQ –exec". GMA News. Retrieved March 31, 2022.
  73. ^ Amojelar, Darwin G. (July 11, 2021). "MRT 3 rehabilitation completed December". Manila Standard. Retrieved July 13, 2021.
  74. ^ Galvez, Daphne (March 1, 2022). "MRT 3 rehabilitation is finished, says Tugade". Philippine Daily Inquirer. Retrieved March 1, 2022.
  75. ^ Grecia, Leandre (March 22, 2022). "DOTr marks the completion of the MRT-3 Rehabilitation Project". Top Gear Philippines. Retrieved March 22, 2022.
  76. ^ Panti, Llanesca T. (March 22, 2022). "Duterte announces free MRT-3 rides from March 28 to April 30 amid rehab work completion". GMA News. Retrieved March 22, 2022.
  77. ^ Locus, Sundy (June 21, 2022). "Libreng Sakay of PUVs, MRT-3 to end on June 30, 2022". GMA News. Retrieved June 22, 2022.
  78. ^ Domingo, Ronnel W. (May 27, 2023). "Japan lends P6.9B to bankroll MRT-3 rehab". Philippine Daily Inquirer. Retrieved May 27, 2023.
  79. ^ Abadilla, Emmie V. (May 31, 2023). "DOTR, Sumitomo sign P7.38-B MRT-3 extended rehab contract". Manila Bulletin. Retrieved May 31, 2023.
  80. ^ "Second MRT-3 rehab to enable capacity boost to 500,000 passengers per day". BusinessWorld Online. May 31, 2023.
  81. ^ Luna, Franco (March 29, 2022). "MRT-3 deploys 4-car, 3-car train sets simultaneously". The Philippine Star. Retrieved March 29, 2022.
  82. ^ Valmonte, Kaycee; Luna, Franco (April 14, 2022). "Tugade sorry for inconvenience brought by MRT-3 closure on last workday of Holy Week". The Philippine Star. Retrieved April 15, 2022.
  83. ^ "MRT, LRT-2 to suspend operations during Holy Week holidays". ABS-CBN News. March 13, 2023. Retrieved March 13, 2023.
  84. ^ Grecia, Leandre (December 21, 2021). "Here are the LRT-1, LRT-2, MRT-3 schedules for Christmas 2021". Top Gear Philippines. Retrieved December 21, 2021.
  85. ^ Olchondra, Riza T. (May 29, 2009). "MRT-3 rides to go 24 hours starting June 1". Philippine Daily Inquirer. Archived from the original on May 30, 2009. Retrieved May 31, 2009.
  86. ^ Kwok, Abigail (June 3, 2009). "MRT-3 stops 24-hour run". Philippine Daily Inquirer. Archived from the original on October 27, 2014. Retrieved March 11, 2014.
  87. ^ Camus, Miguel R.; Calleja, Niña P. (February 21, 2014). "DOTC extends MRT-3 operating hours". Philippine Daily Inquirer. Retrieved March 11, 2014.
  88. ^ Regalado, Pia (August 17, 2023). "Why the MRT-3 Can't Operate 24/7". spot.ph. Retrieved June 27, 2024.
  89. ^ Casucian, Jiselle Anne (August 17, 2023). "MRT-3 says it can't operate 24/7 due to nighttime maintenance". GMA Integrated News. Retrieved June 27, 2024.
  90. ^ Relativo, James (August 19, 2023). "Group to MRT-3 management: Extend services until midnight". The Philippine Star. Retrieved June 27, 2024.
  91. ^ Satre, Gary L. (June 1998). "The Metro Manila LRT System—A Historical Perspective" (PDF). Japan Railway and Transport Review. 16: 33–37. Archived from the original (PDF) on May 5, 2006. Retrieved August 14, 2014.
  92. ^ ALAMIN: Narito ang listahan ng mga priority passengers na maaaring makasakay sa priority area na unang bagon o train car ng mga tren ng MRT-3. Facebook. DOTr MRT-3. February 16, 2022. Retrieved February 16, 2022.
  93. ^ Cortez, Joseph (August 22, 2020). "All MRT-3 escalators, elevators now working". Daily Tribune. Archived from the original on April 19, 2022. Retrieved April 19, 2022.
  94. ^ Lapeña, Carmela G. (February 11, 2012). "Bike to work? Why not? MRT now allows folding bikes". GMA News Online. Retrieved May 15, 2022.
  95. ^ "Platform doors installed in MRT station". ABS-CBN News. June 26, 2013. Retrieved September 20, 2020.
  96. ^ a b Nicholls, AJ; Bacungan, VJ (November 15, 2017). "Gov't considers screen doors at MRT Ayala station after accident". CNN Philippines. Archived from the original on March 25, 2022. Retrieved September 20, 2020.
  97. ^ Ulanday, Abelardo S. (December 9, 2001). "The best things in life are Libre". Philippine Daily Inquirer. Retrieved August 14, 2014 – via Google News Archive.
  98. ^ World Bank (December 2, 2004). "A Tale of Three Cities: Urban Rail Concessions in Bangkok, Kuala Lumpur and Manila – Final Report" (PDF). p. 17. Archived from the original (PDF) on April 24, 2006. Retrieved August 18, 2014. (Prepared by Halcrow Group Limited).
  99. ^ "Months ago, experts warned line was unsafe". ABS-CBN News and Current Affairs. August 13, 2014. Retrieved August 17, 2014.
  100. ^ Hegina, Aries Joseph (August 14, 2014). "Abaya: MRT3 is safe, riding it 'a personal decision'". Philippine Daily Inquirer. Retrieved August 21, 2014.
  101. ^ Cupin, Bea (August 14, 2014). "Abaya admits MRT-3 upgrade overdue". Rappler. Retrieved August 17, 2014.
  102. ^ Manabat, Johnson (December 18, 2013). "MRT-3 enforces new crowd control scheme". ABS-CBN News and Current Affairs. Retrieved August 17, 2014.
  103. ^ Camus, Miguel R. (May 6, 2014). "All is set for MRT-3 express train run". Philippine Daily Inquirer. Retrieved August 18, 2014.
  104. ^ Camus, Miguel R. (December 20, 2013). "MRT-3 boss defends 'crowd control' amid jeering riders". Philippine Daily Inquirer. Retrieved August 17, 2014.
  105. ^ a b "MRT3 Reminders". Metro Rail Transit Line 3. Metro Rail Transit Corporation. Archived from the original on August 19, 2014. Retrieved August 17, 2014.
  106. ^ Antiporda, Jefferson (August 10, 2005). "MRT-3 issues directive imposing ban on tin cans". The Manila Times. Manila Times Publishing Corporation. Archived from the original on August 19, 2006. Retrieved May 19, 2006.
  107. ^ a b Manabat, Jacque (May 13, 2021). "MRT management looking for witnesses after train vandalism". ABS-CBN News. Retrieved May 13, 2021.
  108. ^ Fe, Kaye (May 19, 2021). "MRT-3 beefs up security following May 12 vandalism incident". Eagle News. Eagle Broadcasting Corporation. Archived from the original on August 15, 2021. Retrieved August 15, 2021.
  109. ^ "No suspicious activities after hoax bomb threat hits MRT-3, says DOTr". CNN Philippines. September 8, 2023. Archived from the original on November 10, 2023. Retrieved September 9, 2023.
  110. ^ Del Puerto, Luige A.; Quismundo, Tarra V. (November 13, 2004). "New task force formed to keep LRT, MRT safe". Philippine Daily Inquirer. Archived from the original on January 4, 2005. Retrieved May 19, 2006.
  111. ^ "MRT-3 allows pets inside trains". CNN Philippines. July 13, 2021. Archived from the original on July 19, 2021. Retrieved July 19, 2021.
  112. ^ a b c "MRT3 Ridership". DOTr. Archived from the original on November 4, 2021. Retrieved November 4, 2021.
  113. ^ Dela Cruz, Raymond Carl (June 25, 2020). "4 Metro Manila rail lines transport 2.8M passengers since June 1". Philippine News Agency. Archived from the original on November 4, 2021. Retrieved November 4, 2021.
  114. ^ "MRT-3 serves record 157K passengers since Covid lockdown". www.pna.gov.ph. January 19, 2021. Retrieved November 4, 2021.
  115. ^ a b c Fernandez, Daniza (January 24, 2022). "45.6 million commuters ride MRT-3 in 2021". Philippine Daily Inquirer. Retrieved January 24, 2022.
  116. ^ Cayabyab, Marc Jayson (June 8, 2022). "No unloading incidents as ridership peaks at MRT". The Philippine Star. Retrieved June 8, 2022.
  117. ^ Libreng Sakay Update. Facebook. July 1, 2022. Retrieved July 1, 2022.
  118. ^ Sarao, Zacarian (January 5, 2023). "MRT-3 ridership breaches 98 million mark in 2022". Philippine Daily Inquirer. Retrieved January 5, 2023.
  119. ^ "MRT-3, LRT-2 offer free rides to women on March 8". GMA News Online. March 7, 2021. Retrieved June 10, 2021.
  120. ^ "MRT, LRT 1 and 2 to offer free rides on June 12". ABS-CBN News. June 11, 2019. Retrieved June 10, 2021.
  121. ^ "MRT3 to offer free rides on Independence Day". GMA News Online. June 10, 2021. Retrieved June 10, 2021.
  122. ^ Sabillo, Kristine Angeli (December 28, 2013). "MRT, LRT offer free rides on Rizal Day". Philippine Daily Inquirer. Retrieved July 24, 2021.
  123. ^ Rey, Aika (June 27, 2019). "Free LRT 2, MRT, PNR rides for students starting July 1". Rappler. Retrieved June 10, 2021.
  124. ^ Laurel, Drei (June 28, 2019). "Students must register for free MRT-3, LRT-2, and PNR rides". Top Gear Philippines. Retrieved June 10, 2021.
  125. ^ Mercado, Neil Arwin (July 1, 2022). "Marcos extends free EDSA Carousel bus rides, OKs free train rides for students". Philippine Daily Inquirer. Retrieved July 1, 2022.
  126. ^ Rosales, Elijah Felice (July 14, 2022). "Free Train Rides For Students Limited To LRT-2". One News. Retrieved August 17, 2022.
  127. ^ "MRT-3 ready for reopening of classes, expects 1,400 students daily". Politiko Metro Manila. August 17, 2022. Retrieved August 17, 2022.
  128. ^ Araneta, Sandy (October 21, 2005). "DOTC: MRT-3 fare could increase by P10 in 2006". The Philippine Star. PhilStar Daily, Inc. Retrieved May 19, 2006.
  129. ^ Casanova, Sheryll B. (November 12, 2003). "MRTC borrows value tickets from LRTA". The Manila Times. Manila Times Publishing Corporation. Archived from the original on January 5, 2004. Retrieved May 18, 2006.
  130. ^ Amojelar, Darwin G. (September 21, 2012). "Expect long queues at MRT-3 amid shortage of tickets – MRT3". TV5 News and Information. Archived from the original on September 13, 2014. Retrieved September 13, 2014.
  131. ^ Agcaoili, Lawrence (July 20, 2014). "DOTC earmarks P25M to buy additional MRT-3 tickets". ABS-CBN News and Current Affairs. Retrieved September 13, 2014.
  132. ^ "MRT3 woes". The Manila Times. Manila Times Publishing Corporation. November 16, 2005. Archived from the original on December 8, 2015. Retrieved July 2, 2006.
  133. ^ Reyes, Mary Ann Ll. (November 17, 2006). "Globe bares G-Pass ticketing for MRT3". The Philippine Star. PhilStar Daily, Inc. Retrieved September 13, 2014.
  134. ^ Reyes, Mary Ann Ll. (March 31, 2007). "Smart ties up with MetroPass on MRT-3". The Philippine Star. PhilStar Daily, Inc. Retrieved September 13, 2014.
  135. ^ Amojelar, Darwin G. (January 29, 2013). "Ayala group to bid for common ticket system". TV5 News and Information. Archived from the original on October 19, 2014. Retrieved September 23, 2014.
  136. ^ "MRT-3 passengers start using beep cards". GMA News Online. October 3, 2015. Retrieved June 23, 2022.
  137. ^ Manabat, Jacque (July 19, 2022). "Depleted supply of Beep cards anticipated due to global chip shortage". ABS-CBN News. Retrieved August 20, 2022.
  138. ^ Rosales, Elijah Felice (August 20, 2022). "DOTr warns of 'beep' card shortage". The Philippine Star. Retrieved August 20, 2022.
  139. ^ a b Serfino, Dennis C. (May 1, 2003). "Metro Star still can't get enough revenue". Manila Standard. Kamahalan Publishing Corporation. Retrieved April 23, 2014 – via Google News Archive.
  140. ^ "LRT-MRT FARES TO BE INCREASED ON JAN.4". dotc.gov.ph. Department of Transportation and Communications (DOTC). Archived from the original on December 25, 2014. Retrieved March 10, 2015.
  141. ^ a b Tuazon, Brenda P. (July 16, 2000). "Estrada Orders MRT3 Firm to Reduce Metrostar Fares". Manila Bulletin. Manila Bulletin Publishing Corporation. Archived from the original on February 9, 2019. Retrieved September 1, 2021.
  142. ^ a b Mandri-Perrott, Cledan (2000). Private Sector Participation in Light Rail-Light Metro Transit Initiatives. Washington, D.C.: World Bank. p. 94. ISBN 0-8213-8085-0.
  143. ^ Recuenco, Aaron (April 4, 2022). "Almost 2M passengers served during the first week of MRT-3's month-long free ride". Manila Bulletin. Archived from the original on June 21, 2022. Retrieved April 4, 2022.
  144. ^ a b Diokno, Benjamin E. (December 17, 2013). "Folly of government subsidy". BusinessWorld. BusinessWorld Publishing Corporation. Retrieved April 25, 2014.
  145. ^ Valderrama, Tita C. (February 9, 2014). "Messed up mass transport system". The Manila Times. Manila Times Publishing Corporation. Archived from the original on April 23, 2014. Retrieved April 23, 2014.
  146. ^ Agcaoili, Lawrence (December 14, 2013). "DOTC says MRT, LRT fare hike to yield P2-B add'l revenues". The Philippine Star. PhilStar Daily, Inc. Retrieved April 23, 2014.
  147. ^ Casauay, Angela (October 25, 2012). "Visayan solons back P10 MRT3 fare hike". Rappler. Retrieved September 23, 2014.
  148. ^ Aquino III, Benigno S. (July 22, 2013). [English] Benigno S. Aquino III, Fourth State of the Nation Address, July 22, 2013 (Speech). State of the Nation Address. Quezon City. Retrieved September 23, 2014. Each trip that one passenger makes on the LRT is estimated to cost 40 pesos. What does each passenger pay? 15 pesos. This means that the government subsidizes the remaining 25 pesos. As for the line, the true cost of one trip is 60 pesos: 15 pesos paid by passengers, 45 pesos by the government—in the end, each and every Filipino pays a share of the subsidy. Whether you live in Mindanao or Visayas, and not once have you ever stepped onto the LRT or MRT, you help to fund this.
  149. ^ Cruz, Neal H. (November 18, 2012). "No improved MRT3 service, no fare hike". Philippine Daily Inquirer. Retrieved September 23, 2014.
  150. ^ Noriega, Richa (January 31, 2023). "MRT-3 files petition for fare rate increase". GMA Integrated News. Retrieved February 1, 2023.
  151. ^ Gulla, Vivienne (December 1, 2023). "MRT-3 fare hike to be implemented in 2024: DOTr". ABS-CBN News. Retrieved December 1, 2023.
  152. ^ "MRT3 stress and Camp John Hay turmoil". The Manila Times. Manila Times Publishing Corporation. June 21, 2005. Retrieved July 2, 2006.[permanent dead link]
  153. ^ Dela Cruz, Raymond Carl (March 31, 2022). "MRT-3 posts single-day record high ridership of 290K passengers". Philippine News Agency. Retrieved April 1, 2022.
  154. ^ Macapagal, Maan (February 2, 2013). "MRT-3 to get additional 52 coaches". ABS-CBN News.
  155. ^ Agcaoili, Lawrence (September 12, 2013). "Inekon: PH can save $5M a year with new MRT trains". The Philippine Star – via ABS-CBN News.
  156. ^ "Passenger information system to be installed in LRT, MRT". BusinessWorld. March 27, 2019. Retrieved December 12, 2020.
  157. ^ Jocson, Mon (February 26, 2015). "MRT uses old tracks in sectional rail replacement". UNTV News. Archived from the original on January 14, 2022. Retrieved January 14, 2022.
  158. ^ a b c d e Pateña, Aerol John (February 9, 2018). "Bombardier to supply parts, signalling system for MRT upgrade anew". Philippine News Agency. Retrieved January 12, 2022.
  159. ^ "Projects in Mass-transit signalling" (PDF). Bombardier Transportation. Archived from the original (PDF) on November 23, 2021. Retrieved February 22, 2022.
  160. ^ "Mass transit signalling". Bombardier Transportation. Archived from the original on January 1, 2022. Retrieved February 22, 2022.
  161. ^ Department of Transportation and Communications (March 2013). MRT3 System Temporary Maintenance Provider – One (1) Year (PDF) (Report). Archived from the original (PDF) on December 27, 2021. Retrieved February 22, 2022.
  162. ^ "TERMS OF REFERENCE - Procurement of Signalling System Maintenance Provider Services for DOTr MRT3". Department of Transportation (Philippines). 2018. Retrieved February 21, 2022.
  163. ^ "MRT-3 signaling system upgrade begins". Department of Transportation and Communications. October 1, 2015. Archived from the original on February 19, 2022. Retrieved February 19, 2022 – via the Official Gazette of the Republic of the Philippines.
  164. ^ "MAINTENANCE OF MRT3 SIGNALING SYSTEM FOR 24 MONTHS". Department of Transportation (Philippines). Archived from the original on December 27, 2021. Retrieved January 12, 2022.
  165. ^ Montaño, Len (September 17, 2019). "DOTr: Signalling at commucations system ng MRT-3 ikakabit na". Radyo Inquirer. Philippine Daily Inquirer, Inc. Retrieved March 2, 2022.
  166. ^ Dela Cruz, Raymond Carl (May 25, 2021). "MRT-3 completes signal lights upgrade". Philippine News Agency. Retrieved February 19, 2022.
  167. ^ Dela Cruz, Raymond Carl (March 5, 2021). "MRT-3 touts increased safety with continuous rehab of rail line". Philippine News Agency. Retrieved April 12, 2022.
  168. ^ "MAGANDANG BALITA! 100% testing & commissioning ng bago at upgraded signaling system ng MRT-3, nakamit na!". Facebook. November 2, 2021. Archived from the original on February 26, 2022. Retrieved January 12, 2022.
  169. ^ "Alstom in the Philippines" (PDF). Alstom. November 2021. Retrieved February 19, 2022.
  170. ^ Dela Cruz, Raymond Carl (July 8, 2021). "MRT-3 rehabs service with new reinforced sleepers". Philippine News Agency. Retrieved January 12, 2022.
  171. ^ De La Cruz, Jovee Marie (February 25, 2015). "MRT 3 rail-replacement project set this weekend". Business Mirror. Retrieved February 27, 2022.
  172. ^ "MRT-3 to open late on Sunday due to rail replacement works". Department of Transportation and Communications. March 19, 2015. Retrieved February 27, 2022.
  173. ^ "MRT3 rail replacement set to start". Rappler. July 5, 2015. Retrieved February 3, 2021.
  174. ^ Morial, Daniel (August 22, 2014). "MRT-3 speed limit down from 60kph to 40kph". YugaTech. Retrieved November 30, 2021.
  175. ^ "Bid Bulletin No. 1" (PDF). Reinsurance of the Industrial All Risk Insurance of the Department of Transportation – MRT3. Government Service Insurance System. September 22, 2017. Retrieved February 3, 2022.
  176. ^ "New rails for MRT-3 arrive in PH". Philippine News Agency. July 10, 2019. Retrieved January 10, 2022.
  177. ^ Subingsubing, Krixia (May 20, 2020). "DOTr: Over half of MRT 3's tracks replaced". Philippine Daily Inquirer. Retrieved June 7, 2020.
  178. ^ a b Balinbin, Arjay L. (May 19, 2020). "MRT-3 train speed, capacity expected to double by December". BusinessWorld. Retrieved June 7, 2020.
  179. ^ de Guzman, Robie (October 9, 2020). "MRT-3 to implement partial ops on Oct. 10 to 11". UNTV News. Archived from the original on April 1, 2022. Retrieved April 1, 2022.
  180. ^ "MRT reschedules suspension of operations to Nov. 14-15; Nov. 28-30". CNN Philippines. November 10, 2020. Archived from the original on April 1, 2022. Retrieved April 1, 2022.
  181. ^ Dumlao, Miggy (December 8, 2020). "MRT-3 now runs at 60 kph speed". Philippine Daily Inquirer. Retrieved November 4, 2021.
  182. ^ Razon, Kristelle Anne (November 10, 2022). "Privatization of MRT-3 operations, maintenance eyed". Inquirer. Retrieved November 15, 2022.
  183. ^ Porcalla, Delon (August 23, 2017). "Lawmaker wants MRT-3 privatized". The Philippine Star. Retrieved November 15, 2022.
  184. ^ "The study on the standardization for Integrated Railway Network of Metro Manila (SIRNMM) final report" (PDF). March 2001. Retrieved June 18, 2024.
  185. ^ "The study on the standardization for Integrated Railway Network of Metro Manila (SIRNMM) final report : main report".
  186. ^ Torres, Ted P. (September 21, 2004). "LRT-MRT link is nat'l priority – NEDA". Philippine Daily Inquirer. Archived from the original on September 25, 2004. Retrieved May 12, 2006.
  187. ^ "After gov't takeover of NAIA Terminal 3, PGMA orders immediate completion of EDSA MRT3 extension" (Press release). Department of Transportation and Communications. January 4, 2005. Retrieved May 19, 2006.[permanent dead link]
  188. ^ Ronda, Rainier Allan (February 11, 2010). "LRT trains can run on MRT to solve overloading woes". The Philippine Star. Retrieved February 6, 2022.
  189. ^ Chanco, Boo (January 2, 2013). "P-Noy can't deliver MRT-3 upgrades". Philstar. Archived from the original on May 18, 2018. Retrieved January 2, 2013.
  190. ^ "Ayala, San Miguel, Meralco, 21 others interested in MRT-3, LRT-1". ABS-CBN News. April 14, 2011. Archived from the original on January 25, 2020. Retrieved February 18, 2022.
  191. ^ "DOTC chief de Jesus resigns". ABS-CBN News. June 1, 2011. Archived from the original on February 18, 2022. Retrieved February 18, 2022.
  192. ^ Montecillo, Paolo G. (July 13, 2011). "DOTC reviews MRT-LRT central station project". Philippine Daily Inquirer. Retrieved February 18, 2022.
  193. ^ Mercurio, Richmond (June 10, 2024). "MPIC proposes to integrate operations of MRT-3, LRT-1". Philstar.com. Retrieved June 10, 2024.
  194. ^ "For seamless Metro travel: PPP Center endorses Pangilinan group's integration proposal for MRT3, LRT1". June 14, 2024.
  195. ^ "METRO MANILA URBAN TRANSPORTATION INTEGRATION STUDY" (PDF). www.jica.go.jp. March 1999. Retrieved June 18, 2024.
  196. ^ "Company Profile - Transport and Traffic Planners (TTPI) Inc". www.ttpiph.com.
  197. ^ a b "ROADMAP FOR TRANSPORT INFRASTRUCTURE DEVELOPMENT FOR METRO MANILA AND ITS SURROUNDING AREAS (REGION III & REGION IV-A)".
  198. ^ Camus, Miguel R. (September 22, 2021). "SM Group offers to build monorail and road flyover in Pasay". inquirer.net. Retrieved November 4, 2021.
  199. ^ a b Ho, Abigail L. (February 12, 2002). "MRT gets $170-M German funding". Philippine Daily Inquirer. pp. B3. Retrieved July 17, 2024.
  200. ^ "Metrostar extension to NAIA proposed". Philippine Daily Inquirer. January 20, 2000. pp. B3.
  201. ^ Amojelar, Darwin G. (December 28, 2010). "Govt creates team for MRT-3 due diligence, sets June takeover". The Manila Times. Manila Times Publishing Corporation. Retrieved January 15, 2011.[permanent dead link]
  202. ^ Dagcutan, Aura Marie P. (January 13, 2011). "LRTA chief takes over MRT-3". BusinessWorld. BusinessWorld Publishing Corporation. Archived from the original on September 23, 2015. Retrieved January 18, 2011.
  203. ^ LRT trial run sa MRT 3 North Avenue depot. April 22, 2012.
  204. ^ Camus, Miguel R. (May 27, 2014). "Vitangcol replaced as head of MRT-3". inquirer.net. Retrieved May 27, 2014.
  205. ^ Tabile, Justine Irish D. (July 30, 2023). "Build-Lease-Transfer deal expiry could lead to absorption of MRT-3 by LRTA". BusinessWorld. Retrieved June 26, 2024.
  206. ^ Tan, Kimberly Jane (November 21, 2013). "NEDA approves MRT 7, LRT-1 extension projects". GMA News and Public Affairs. Retrieved January 1, 2014.
  207. ^ Lectura, Lenie (September 23, 2013). "DOTC ready to refund SM's P200-M naming-rights fee for common station". BusinessMirror. Philippine Business Daily Mirror Publishing, Inc. Archived from the original on January 2, 2014. Retrieved January 1, 2014.
  208. ^ Marasigan, Gelo; Remitio, Rex (September 28, 2016). "Finally: A common station for LRT, MRT lines". CNN Philippines. Archived from the original on April 10, 2018. Retrieved April 10, 2018.
  209. ^ Flores, Mikhail Franz; dela Paz, Chrisee Jalyssa (August 2, 2014). "High court stops transfer of common train station site". BW. Archived from the original on June 16, 2018. Retrieved August 2, 2014.
  210. ^ Fe, Kaye (September 29, 2017). "Construction of P2.8-B Grand Unified Central Station to begin after almost a decade of delay". EBC. Retrieved September 29, 2017.
  211. ^ Jiao, Claire (September 29, 2017). "LRT-MRT common station breaks ground". CNN Philippines. Archived from the original on April 11, 2018. Retrieved April 10, 2018.
  212. ^ Rey, Aika (April 26, 2021). "LRT-MRT common station partial operations postponed to Q4 2021". Rappler. Retrieved May 26, 2021.
  213. ^ Santos, Reynaldo Jr. (August 13, 2014). "TIMELINE: MRT3 mishaps". Rappler. Retrieved September 17, 2019.
  214. ^ "Metrostar Express resumes operations". The Philippine Star. January 12, 2000. Retrieved October 28, 2024.
  215. ^ Calica, Aurea (October 24, 2000). "'Human traffic' at MRT Taft station deplored". The Philippine Star. Retrieved October 28, 2024.
  216. ^ Crisostomo, Sheila; Mendez, Christina (March 20, 2003). "Vagrant killed in MRT mishap". The Philippine Star. Retrieved October 28, 2024.
  217. ^ Lee-Brago, Pia (August 30, 2003). "Death plunge". The Philippine Star. Retrieved October 28, 2024.
  218. ^ Alquitran, Non (March 12, 2004). "150 cops secure strike-hit MRT". The Philippine Star. Retrieved October 28, 2024.
  219. ^ Adraneda, Katherine (May 21, 2004). "Bad weather stalls MRT". The Philippine Star. Retrieved October 28, 2024.
  220. ^ Ronda, Rainier Allan (August 13, 2004). "MRT stalls anew". The Philippine Star. Retrieved October 28, 2024.
  221. ^ Punongbayan, Michael (July 7, 2005). "MRT stalls anew". The Philippine Star. Retrieved October 28, 2024.
  222. ^ Araneta, Sandy (September 24, 2005). "Billboard falls on MRT railway". The Philippine Star. Retrieved October 28, 2024.
  223. ^ Balasa, Edwin (July 7, 2005). "MRT stalls anew". The Philippine Star. Retrieved October 28, 2024.
  224. ^ Ronda, Rainier (August 19, 2010). "Toppled structures for billboards damage MRT equipment". The Philippine Star. Retrieved October 28, 2024.
  225. ^ [hhttps://newsinfo.inquirer.net/252084/amid-heavy-rains-rapist-lurks-at-mrt-santolan-station "Amid heavy rains, rapist lurks at MRT Santolan station"]. Philippine Daily Inquirer. August 19, 2012. Retrieved October 28, 2024.
  226. ^ Geronimo, Gian (November 3, 2012). "MRT train coach catches fire near Kamuning Station". GMA News Online. Retrieved September 6, 2019.
  227. ^ Elona, Jamie (May 8, 2013). "Man dies after jumping in front of oncoming MRT train in Guadalupe". Inquirer.net. Retrieved January 26, 2024.
  228. ^ Fernandez, Amanda (March 26, 2014). "10 passengers hurt as MRT train makes sudden stop". GMA News Online. Retrieved June 4, 2020.
  229. ^ Pineda, Mj Lising (August 13, 2014). "MRT-3 Gets Derailed". Buhaykolehiyo. Archived from the original on October 25, 2014.
  230. ^ Camus, Miguel R. (August 19, 2014). "DOTC: Human error blamed for MRT-3 train accident; 4 train workers face raps". inquirer.net. Retrieved June 6, 2020.
  231. ^ Hegina, Aries Joseph (September 3, 2014). "MRT train continues run with one of its doors open". Philippine Daily Inquirer. Retrieved November 30, 2021.
  232. ^ Rey, Aika (November 14, 2017). "Woman loses right arm in MRT3 accident". Rappler. Retrieved November 5, 2021.
  233. ^ Yee, Jovic (November 15, 2017). "Severed arm of woman in MRT-3 accident reconnected". Philippine Daily Inquirer. Retrieved November 5, 2021.
  234. ^ Lagrimas, Nicole-Anne (November 16, 2017). "Up to 140 riders evacuated from 'detached train'". GMA News Online. Retrieved November 16, 2017.
  235. ^ Rey, Aika (August 8, 2018). "Aircon leak causes 'rain' inside MRT3". Rappler. Retrieved June 19, 2021.
  236. ^ Orellana, Faye (September 26, 2018). "7 hurt as two MRT-3 maintenance vehicles collide". Philippine Daily Inquirer. Retrieved October 10, 2021.
  237. ^ "Ilang pasahero ng MRT, nag-panic dahil sa nangyaring aberya kaninang umaga". GMA News Online. September 6, 2019. Retrieved September 12, 2019.
  238. ^ Tuquero, Loreben (September 19, 2019). "Overhaul overdue: Daily maintenance fails to prevent MRT3 short circuit". Rappler. Retrieved August 2, 2021.
  239. ^ Galvez, Daphne (November 4, 2019). "MRT-3 resumes normal ops from North to Taft stations after train emits smoke". Inquirer.net. Retrieved November 5, 2019.
  240. ^ de Guzman, Robie (November 7, 2019). "MRT-3 says train smoke emission due to short circuit in traction motor". UNTV News. Archived from the original on January 18, 2022. Retrieved January 17, 2022.
  241. ^ Cerrudo, Aileen (May 11, 2021). "2 MRT passengers face charges for going down train tracks to take a selfie". UNTV News and Rescue. Archived from the original on May 11, 2021. Retrieved August 12, 2021.
  242. ^ Fernandez, Daniza (October 10, 2021). "MRT-3 fire injures 8 passengers". Philippine Daily Inquirer. Retrieved October 10, 2021.
  243. ^ Montemayor, Ma. Teresa (October 10, 2021). "MRT-3 resumes full operation after fire". Philippine News Agency. Retrieved October 10, 2021.
  244. ^ "One hurt after unidentified suspect hurls stone at MRT3 train coach". GMA News and Public Affairs. November 21, 2021. Retrieved November 21, 2021.
  245. ^ "Suspek sa pambabato sa MRT3 na ikinasugat ng 1 pasahero, arestado". GMA News (in Filipino). November 21, 2021. Retrieved November 21, 2021.
  246. ^ Cabuenas, Jon Viktor D. (June 12, 2022). "MRT3 suspends operations after 2 people reportedly fall onto tracks from flyover". GMA News. Retrieved June 12, 2022.
[edit]